Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 569
Message text: Project structure contains several calendars
You have entered different factory calendars for the dates of the
individual WBS elements. You could get dates for the WBS elements which
vary considerably from each other after you have rolled them up,
adjusted or shifted them.
Error message extract from SAP system. Copyright SAP SE.
CJ569
- Project structure contains several calendars ?The SAP error message CJ569 indicates that there are multiple calendars assigned to different elements of a project structure. This can occur when different activities or work breakdown structure (WBS) elements within the same project are assigned to different calendars, which can lead to inconsistencies in scheduling and planning.
Cause:
- Multiple Calendars: Different project elements (like WBS elements, activities, etc.) are assigned to different calendars. This can happen if the project was set up with elements that have different working times or if changes were made to the calendar assignments after the project was created.
- Inconsistent Settings: If the project structure was modified, and some elements were assigned to a different calendar than others, it can lead to this error.
- Project Structure Changes: Changes in the project structure, such as adding new activities or WBS elements with different calendar settings, can trigger this error.
Solution:
Standardize Calendars: Ensure that all elements of the project structure are assigned to the same calendar. You can do this by:
- Navigating to the project in the Project System (PS) module.
- Checking the calendar assignments for each WBS element and activity.
- Changing the calendar for the elements that have a different calendar assigned to match the others.
Use the Same Working Time: If you have a specific working time that should apply to the entire project, make sure all elements are using that same working time calendar.
Review Project Settings: Go through the project settings and ensure that the calendar settings are consistent across all levels of the project structure.
Transaction Codes: You can use transaction codes like CJ20N (Project Builder) to view and edit the project structure and calendar assignments.
Consult Documentation: If you are unsure about how to change the calendar assignments, refer to SAP documentation or consult with your SAP administrator or a functional consultant.
Related Information:
By ensuring that all elements of your project structure are aligned with the same calendar, you should be able to resolve the CJ569 error and proceed with your project planning and execution.
Get instant SAP help. Start your 7-day free trial now.
CJ568
WBS element &1: Activity &2 in network &3 is not in time frame
What causes this issue? Activity &V2& in network &V3& no longer lies within the time frame of WBS element &V1&.How to fix thi...
CJ567
There are no activities for the selected WBS elements
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ570
No activities. Scheduling was not carried out.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ571
No actual dates could be determined for WBS element &
What causes this issue? You cannot copy.System Response The system issues an error message and will not allow you to continue with this transaction ...
Click on this link to search all SAP messages.