How To Fix CJ412 - & WBS elements could not be moved to higher levels


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CJ - Project master data and structure

  • Message number: 412

  • Message text: & WBS elements could not be moved to higher levels

  • Show details Hide details
  • What causes this issue?

    You cannot level up the WBS elements you have selected.
    If you want to level up WBS elements, you must consider the
    following points:
    You can only level up WBS elements one level higher, to the level
    immediately before the WBS element you selected.
    Subordinate WBS elements in the hierarchy cannot be leveled up
    You cannot level up from initial WBS elements.

    System Response

    INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CJ412 - & WBS elements could not be moved to higher levels ?

    The SAP error message CJ412 indicates that WBS (Work Breakdown Structure) elements cannot be moved to higher levels in the project hierarchy. This error typically arises due to certain constraints or conditions that prevent the movement of WBS elements. Here are the common causes, potential solutions, and related information for this error:

    Causes of Error CJ412

    1. Dependencies and Relationships: The WBS element may have existing dependencies or relationships with other elements that prevent it from being moved. For example, if there are assigned activities, costs, or other linked elements, the system may restrict the movement.

    2. Status of WBS Elements: If the WBS element or its parent has a status that does not allow changes (e.g., "Closed" or "Completed"), the system will prevent the movement.

    3. Hierarchy Constraints: The structure of the project may impose certain constraints that do not allow a WBS element to be moved to a higher level. This could be due to organizational policies or project management rules.

    4. Authorization Issues: The user may not have the necessary authorizations to perform the move operation, leading to the error.

    5. Project Structure: The project structure may not support the movement of WBS elements due to predefined settings or configurations in the project management module.

    Solutions to Error CJ412

    1. Check Dependencies: Review the WBS element for any dependencies or relationships with other elements. If there are linked activities or costs, consider removing or adjusting them before attempting to move the WBS element.

    2. Change Status: If the WBS element or its parent is in a status that restricts changes, you may need to change the status to allow for movement. This may involve changing the status back to "In Process" or similar.

    3. Review Hierarchy Rules: Ensure that the movement of the WBS element complies with the project hierarchy rules. If necessary, consult with project management to understand any constraints.

    4. Check Authorizations: Verify that you have the necessary permissions to move WBS elements. If not, contact your SAP administrator to obtain the required authorizations.

    5. Consult Documentation: Review SAP documentation or help resources for specific guidelines on moving WBS elements. This may provide insights into any additional constraints or requirements.

    6. Use Transaction Codes: Utilize relevant transaction codes (e.g., CJ20N for project management) to check the details of the WBS elements and their statuses.

    Related Information

    • SAP Notes: Check SAP Notes for any known issues or patches related to error CJ412. SAP frequently updates its knowledge base with solutions to common problems.

    • Project Management Best Practices: Familiarize yourself with best practices in project management within SAP to avoid similar issues in the future.

    • Training and Support: Consider training sessions or support from SAP consultants to better understand the project management module and how to manage WBS elements effectively.

    By addressing the underlying causes and following the suggested solutions, you should be able to resolve the CJ412 error and successfully move the WBS elements as needed.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author