How To Fix MD427 - &1: &2 (P4)


SAP Error Message - Details

  • Message type: E = Error

  • Message class: MD - Material Requirements Planning (MRP)

  • Message number: 427

  • Message text: &1: &2 (P4)

  • Show details Hide details
  • Was verursacht dieses Problem?

    The production finish date calculated using the routing lies after the
    order finish date that was calculated using the in-house processing time
    in the material master record.
    As the system uses the order finish date in the planning run, this
    situation may lead to material shortages if production is not finished
    until the production finish date calculated by the system.

    Systemantwort

    This exception is displayed in the MRP list and in the current
    stock/requirements list.

    Wie behebe ich diesen Fehler?

    Check the times in the material master record and in the routing.
    Check whether the order has to be rescheduled in.

    Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE


Smart SAP Assistant

  • Was ist die Ursache und Lösung für den SAP Fehler MD427 - &1: &2 (P4) ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Zugehörige SAP-Fehlermeldungen

Klicken Sie auf die Links unten, um die folgenden verwandten Nachrichten anzuzeigen:
  • MD426 &1: &2 (P3)
    Was verursacht dieses Problem? In Customizing, no specification has been made to allow the adjustment of the order start date to the production sta...

  • MD425 &1: &2 (P2)
    Was verursacht dieses Problem? The system could not find a valid routing when scheduling via the routing or the routing is incorrect.Systemantwort ...

  • MD428 &1: &2 (S9)
    Was verursacht dieses Problem? The following reasons exist: Either a component of the planned order or production order entered is identical to the...

  • MD429 &1: &2 (U6)
    Was verursacht dieses Problem? In the individual segment (make-to-order planning, individual project planning, or direct production or direct procu...

Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker