How to use CJ88 - Settle Projects and Networks


CJ88 - Overview

  • Transaction Code: CJ88

    Description: Settle Projects and Networks

    Release: S/4HANA and ECC 6

    Menu Path:

    • Logistics > Project System > Financials > Period-End Closing > Single Functions > Settlement > Individual Processing
    • Accounting > Investment Management > Investment Projects > Period-End Closing > Single Functions > Settlement > Individual Processing
    • Accounting > Project System > Financials > Period-End Closing > Single Functions > Settlement > Individual Processing
    • Accounting > Joint Venture Accounting > Periodic Processing > CO Processing > Project Settlement > Individual Processing
  • Show technical details Hide technical details
    • Program: SAPLKO71

      Screen: 1000

      Authorization Object: C_PROJ_TCD

    • Development Package: KABR

      Package Description: Appl. Development: R/3 Cost Accounting Order Settlement

      Parent Package: APPL

    • Module/Component: CO-OM-OPA

      Description: Overhead Cost Orders


CJ88 - Details

  • SAP Tcode: CJ88 - Settle Projects and Networks
    
    Overview:
    SAP transaction code CJ88 is used to settle projects and networks in the SAP system. This transaction code is used to close out projects and networks that have been completed, and to transfer the associated costs and revenues to the general ledger. 
    
    Functionality: 
    CJ88 allows users to settle projects and networks in the SAP system. This transaction code is used to close out projects and networks that have been completed, and to transfer the associated costs and revenues to the general ledger. The settlement process can be done manually or automatically, depending on the user's preference. 
    
    Step-by-step How to Use: 
    1. Enter transaction code CJ88 in the command field. 
    2. Select the project or network you want to settle. 
    3. Select the settlement type (manual or automatic). 
    4. Enter the settlement date. 
    5. Enter any additional information, such as cost center or profit center, if necessary. 
    6. Confirm your entries by pressing enter or clicking on “Execute” button. 
    7. Review the settlement results and confirm them by pressing enter or clicking on “Execute” button again. 
    8. The project or network is now settled and closed out in SAP system. 
    
    Other Recommendations: 
    It is important to note that when settling a project or network, all open items must be cleared before the settlement process can be completed successfully. Additionally, it is recommended that users review all

    Already have an account? Login here!

CJ88 - Related Tcodes

  • CJ81 - Update Report List...

  • CJ80 - Availability Control - Overview...

  • CJ8A - Act.-setlmt: Proj. retirmt. from IM...

  • CJ8G - Actual Settlement: Projects/Networks...


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker