How To Fix DPR_SHARED207 - Impossible de relier cycle - ordonnancement


SAP Error Message - Details

  • Message type: E = Error

  • Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

  • Message number: 207

  • Message text: Impossible de relier cycle - ordonnancement

  • Show details Hide details
  • Quelle est la cause de ce problème?

    The links form a <ZH>loop</>; scheduling is not possible.

    Réponse du système

    The links between the project elements form a <ZH>loop</>.

    Le système émet un message d'erreur et ne vous permettra pas de poursuivre cette transaction tant que l'erreur n'est pas résolue.

    The system sees both <ZH>relationships</> between the project elements
    and <ZH>structural relationships</> (single-level) between the project
    elements as <ZH>links</>.
    Example:
    <ZK>Ph1</>
    <ZK> T11</>
    <ZK> T111</>
    <ZK> T12</>
    A relationship has been defined between the task <ZK>T11</> and the task
    <ZK>T12</>. The system creates the following links from this
    relationship (<ZK>T11, T12</>) [(predecessor, successor)]. The system
    then uses the structure relationship to create additional links
    dependent on the scheduling type for the tasks <ZK>T11</> and <ZK>T12</>
    below the phase <ZK>Ph1</> and for the task <ZK>T111</> below the task
    <ZK>T11</>:
    Bottom-up: (<ZK>T11, Ph1</>), (<ZK>T12, Ph1</>), (<ZK>T111, T11</>)
    Top-down: (<ZK>Ph1, T11</>), (<ZK>Ph1, T12</>), (<ZK>T11, T111</>)
    1. Setting up a sort order for processing
    The system tries to sort the project elements within scheduling for
    processing, based on the links. There are now two cases in which the
    message can appear:
    a) During sorting, the system finds at least one project element for
    which a loop via the links (predecessor, successor, relationship) is
    possible.
    b) This kind of sorting cannot be set up. At least one project element
    that does not have a predecessor via the links is required for this.
    2. Creating a relationship
    The message can also appear when you create a relationship. This is the
    case if the system is to create a relationship for two project elements
    P1 and P2 with P1 as the predecessor and P2 as the successor, and a
    higher-level project element PP1 of P1 exists and a higher-level project
    element PP2 of P2 exists and these are linked by a relationship with PP1
    as the successor and PP2 as the predecessor.
    Example:
    <ZK>Ph1</>
    <ZK> T11</>
    <ZK> T111</>
    <ZK> T12</>
    <ZK>Ph2</>
    <ZK> T21</>
    <ZK> T22</>
    A relationship always exists between the phase <ZK>Ph1</> and the phase
    <ZK>Ph2</> in the system with <ZK>Ph1</> as the predecessor and <ZK>Ph2
    </> as the successor. The system then tries to create a relationship
    between the task <ZK>T21</> as predecessor and the task <ZK>T12</> as
    the successor.

    Réponse du système

    The project elements cannot be sorted, therefore, scheduling cannot be
    carried out and the relationship cannot be created. The system resets
    the data.

    Comment corriger cette erreur?

    Remove the loop by deleting the relationships between the project
    elements as appropriate.

    Extrait du message d'erreur du système SAP. Copyright SAP SE.


Smart SAP Assistant

  • Quelle est la cause et la solution de l'erreur SAP DPR_SHARED207 - Impossible de relier cycle - ordonnancement ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Messages d'erreur SAP associés

Cliquez sur les liens ci-dessous pour voir les messages connexes suivants:

Cliquez sur ce lien pour rechercher tous les messages SAP.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker