How To Fix DPR_SHARED205 - &1 &2 : la contrainte de fin est incompatible av. date d'un prédécesseur.


DPR_SHARED205 - Overview

  • Message type: E = Error

  • Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

  • Message number: 205

  • Message text: &1 &2 : la contrainte de fin est incompatible av. date d'un prédécesseur.

  • Show details Hide details
  • Quelle est la cause de ce problème?

    When forward scheduling the project element, the system calculated a
    finish date based on a predecessor relationship and the duration of the
    project element. This finish date occurs after the fixed finish of the
    project element.

    Réponse du système

    The system ignores the predecessor relationship and defines the fixed
    finish date as the calculated finish of the project element. The system
    calculates the start date by using the finish date and subtracting the
    duration of the project element from it.

    Comment corriger cette erreur?

    Check whether the fixed finish date of the project element is realistic.

    Procédure pour les administrateurs système

    Le système émet un message d'erreur et ne vous permettra pas de poursuivre cette transaction tant que l'erreur n'est pas résolue.


    Extrait du message d'erreur du système SAP. Copyright SAP SE.


Smart SAP Assistant

  • Quelle est la cause et la solution de l'erreur SAP DPR_SHARED205 - &1 &2 : la contrainte de fin est incompatible av. date d'un prédécesseur. ?







Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Messages d'erreur SAP associés

Cliquez sur les liens ci-dessous pour voir les messages connexes suivants:

Cliquez sur ce lien pour rechercher tous les messages SAP.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author