Do you have any question about this error?
Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 208
Message text: &1 &2 : dates en dehors du domaine de validité du calendrier.
If you schedule &V1& '&V2&', it would have dates that lie outside of
the validity period of the calendar.
The system does not carry out scheduling.
Check the set dates and duration of the project elements for their
correctness.
If the dates are correct then extend the validity period of the factory
calendar.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
DPR_SHARED208
- &1 &2 : dates en dehors du domaine de validité du calendrier. ?Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED207
Impossible de relier cycle - ordonnancement
Quelle est la cause de ce problème? The links form a <ZH>loop</>; scheduling is not possible.Réponse du système The links between th...
DPR_SHARED206
&1 &2 : la contrainte de début est incompatible av. date d'un successeur.
Quelle est la cause de ce problème? When backward scheduling the project element, the system calculated a start date based on a successor relations...
DPR_SHARED209
Impossible de modifier &1 &2
Quelle est la cause de ce problème? &V1& '&V2&' is opened in display mode only, or its status does not allow you to make ...
DPR_SHARED210
Vous n'êtes pas autorisé à ordonnancer &1 &2.
Quelle est la cause de ce problème? You do not have sufficient authorization to carry out scheduling for &V1& '&V2&'.Rép...