Message type: E = Error
Message class:  CY - Capacity Requirements Planning 
Message number: 347
Message text: Réseau &/& : date de fin postérieure à la date de contrainte
The finish date for the operation has the constraint that it should not
finish after a particular date (constraint date). However the start
date when you want to dispatch the operation leads to a finish date
which is after the constraint date. Therefore it is not possible to
dispatch the operation.
You should change the start date so that the operation finishes before
the constraint date.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
 Get instant SAP help. Sign up for our Free Essentials Plan.
Get instant SAP help. Sign up for our Free Essentials Plan. 
CY346 Réseau &/& : date de fin antérieure à la date de contrainte
Quelle est la cause de ce problème?   The finish date for the operation has the constraint that it should not be before a particular date (constraint...
CY345 Réseau &/& : date de fin 'gelée'
Quelle est la cause de ce problème?   The start date for the operation has the constraint that it should finish on a particular date (constraint date...
CY348 Le poste de travail & dans la division & est bloqué
Quelle est la cause de ce problème?   You are trying to dispatch the capacity requiements to the work center &V1& in plant &V2&. Howe...
CY349 Le poste de travail & dans la division & porte le témoin de suppression
Quelle est la cause de ce problème?   You are trying to dispatch capacity requirements to work center &V1& in plant &V2&. However a d...
Cliquez sur ce lien pour rechercher tous les messages SAP.