Message type: E = Error
Message class:  CY - Capacity Requirements Planning 
Message number: 346
Message text: Réseau &/& : date de fin antérieure à la date de contrainte
The finish date for the operation has the constraint that it should not
be before a particular date (constraint date). However the start date
when you want to dispatch the operation leads to a finish date which is
before the constraint date. Therefore it is not possible to
dispatch the operation.
You should change the start date so that the operation finishes before
the constraint date.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
 Get instant SAP help. Sign up for our Free Essentials Plan.
Get instant SAP help. Sign up for our Free Essentials Plan. 
CY345 Réseau &/& : date de fin 'gelée'
Quelle est la cause de ce problème?   The start date for the operation has the constraint that it should finish on a particular date (constraint date...
CY344 Réseau &/& : date de début postérieure à la date de contrainte
Quelle est la cause de ce problème?   The start date for the operation has the constraint that it should not be after a particular date (constraint d...
CY347 Réseau &/& : date de fin postérieure à la date de contrainte
Quelle est la cause de ce problème?   The finish date for the operation has the constraint that it should not finish after a particular date (constra...
CY348 Le poste de travail & dans la division & est bloqué
Quelle est la cause de ce problème?   You are trying to dispatch the capacity requiements to the work center &V1& in plant &V2&. Howe...