Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 345
Message text: Réseau &/& : date de fin 'gelée'
The start date for the operation has the constraint that it should
finish on a particular date (constraint date). However the start date
when you want to dispatch the operation leads to a finish date which
does not correspond to the constraint date. So it is not possible to
dispatch the operation.
You should change the start date on which you want to dispatch the
operation.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
CY345
- Réseau &/& : date de fin 'gelée' ?Get instant SAP help. Sign up for our Free Essentials Plan.
CY344
Réseau &/& : date de début postérieure à la date de contrainte
Quelle est la cause de ce problème? The start date for the operation has the constraint that it should not be after a particular date (constraint d...
CY343
Réseau &/& : date de début antérieure à la date de contrainte
Quelle est la cause de ce problème? The start date for the operation has the constraint that it should not be before a particular date (constraint ...
CY346
Réseau &/& : date de fin antérieure à la date de contrainte
Quelle est la cause de ce problème? The finish date for the operation has the constraint that it should not be before a particular date (constraint...
CY347
Réseau &/& : date de fin postérieure à la date de contrainte
Quelle est la cause de ce problème? The finish date for the operation has the constraint that it should not finish after a particular date (constra...