Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 406
Message text: &1: &2 (N4)
In the MRP list, this exception message displays,
that the order proposal was newly created in the last planning run
that the finish date of the order proposal lies in the past
This situation may occur if automatic forward scheduling in the
planning run has been switched off in Customizing for the plant in
question.
Check whether the order proposal should have been rescheduled.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
MD406
- &1: &2 (N4) ?Get instant SAP help. Start your 7-day free trial now.
MD405
&1: &2 (N3)
¿Qué causa este problema? In the MRP list, this exception message displays that the order proposal was newly created in the last planning run that ...
MD404
&1: &2 (N2)
¿Qué causa este problema? In the MRP list, this exception message displays: that the planned order was newly created in the last planning run that ...
MD407
&1: &2 (S1)
¿Qué causa este problema? No BOM exists for the material or for the sales order for the process with sales order BOM.Respuesta del sistema BOM exp...
MD408
&1: &2 (S2)
¿Qué causa este problema? No valid BOM could be selected for the planned order.Respuesta del sistema BOM explosion cannot be executed. The convers...