Message type: E = Error
Message class: AP - Investment program messages
Message number: 251
Message text: Imposible asignar porque las medidas ya están asignadas
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
One of the following situations has occurred.
You tried to assign an appropriation request to an investment program
position.
However, the system determined that a top WBS element exists that is
assigned to the appropriation request, and a subordinate WBS element of
this top element is itself assigned to a program position.
<ZH>OR</>
You tried to assign a top WBS element to an appropriation request that
is already assigned to an investment program position.
However, the system determined that a WBS element that is subordinate
to this top WBS element in the hierarchy is already assigned to an
investment program position.
This lower-level WBS element is &V1&.
Within a WBS sub-tree that is defined by a top WBS element, only one of
the following is allowed:
<ZH>Either</> WBS elements are assigned directly to program positions.
<ZH>Or</> the top WBS element is assigned to an appropriation request,
and the appropriation request is then assigned to a program position.
The function is not carried out.
&NOTE&
If the appropriation request has "replaced by measure" status, then it
is possible that the measures assigned to the appropriation request
inherited an existing assignment to an investment program when the
status was set.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
AP251
- Imposible asignar porque las medidas ya están asignadas ?Get instant SAP help. Start your 7-day free trial now.
AP250
Atención: El presupuesto acumulado es menor que el presupuesto global
¿Qué causa este problema? You specified for the reassignment of measures that the budget should be adopted consistently from the sending program po...
AP249
Imposible asignar porque la solicitud de medida ya está asignada
¿Qué causa este problema? You tried to display or change the assignment of a WBS element to a program position. However, the system determined that...
AP252
Imposible ejecutar función aquí
Mensaje autoexplicativo Dado que SAP cree que este mensaje de error específico 'se explica por sí mismo', no se ha proporcionado más información. ...
AP253
Para elemento PEP &1 bloqueos plan en programa inversiones asignado
¿Qué causa este problema? You want to change plan values for WBS element &V1&. An investment program position is directly or indirectly ass...
Haga clic en este enlace para buscar todos los mensajes de SAP.