How To Fix V4232 - Forecast delivery schedule is incompatible with the JIT delivery schedule


SAP Error Message - Details

  • Message type: E = Error

  • Message class: V4 - Nachrichten Verkauf (Variable Meldungen und EDI-Meldungen)

  • Message number: 232

  • Message text: Forecast delivery schedule is incompatible with the JIT delivery schedule

  • Show details Hide details
  • What causes this issue?

    In a scheduling agreement with delivery schedules, for which the
    just-in-time (JIT) and forecast delivery schedules are relevant for
    materials planning according to the validity of the JIT horizon, the
    delivery schedule quantity in the JIT delivery schedule horizon does
    not correspond to that in the JIT delivery schedule.
    However, the delivery schedule has a quantity in transit that has been
    included in the schedule line open quantities but is not included in
    the requirements.

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    For example:
    Forecast dlv. sched Jan 1st JIT dlv. sched Feb 1st (valid to Feb 28)
    Cum. delivered qty 100 Cum. delivered qty 100
    Cum. received qty 10 Cum. received qty 50
    In transit 90 In transit 50
    Schedule lines Schedule lines Requirements
    Date Qty Open qty Date Qty Open qty
    ----------------------- ----------------------- ------
    Feb 1 20 0 0
    Feb 8 20 0 0
    Feb 15 20 10 10
    Feb 22 20 20 20
    Mar 1 100 10 100
    Apr 1 100 100 100
    The problem arises because on March 1, a requirement for 100 exists
    although the open quantity is only 10 when you look at the forecast
    delivery schedule only.
    However, if both delivery schedules are valid and relevant, the
    forecast delivery schedule should also contain a corresponding quantity
    for the February schedule lines in the JIT delivery schedule.
    At the moment, it is not clear to the system how much the customer
    requires for March 1.

    System Response

    The system thinks that there are differences between the open
    quantities and the material planning requirements.

    How to fix this error?

    You can do one of the following:
    Either change the material requirement processing for delivery
    schedules in the scheduling agreement.
    If you can't change the materials requirements processing, ask your
    customer to send you a new forecast delivery schedule that matches the
    JIT delivery schedule.
    If the customer can't send you a matching delivery schedule, you will
    have to adjust the delivery schedule, or enter a new forecast delivery
    manually.

    Procedure for System Administrators


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message V4232 - Forecast delivery schedule is incompatible with the JIT delivery schedule ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author