Message text: You are not allowed to change partially confirmed planned order &1
For the sales order that is being changed, a dynamic assembly order
exists that is linked to the sales order. Confirmations have already
been entered for the assembly order, for which goods issues or
production activities have to be posted. The assembly process triggered
by the sales order therefore cannot update the planned order.
The planned order cannot be updated because the separate goods issue or
the production activities could not then be offset. The availability
situation cannot be confirmed and is therefore terminated.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
First complete the postings that are still open (Logistics -->
Production --> Repetitive Manufacturing --> Data Entry --> Decoupled
Confirmation). Then carry out an availability check in the sales order
to restore the confirmed quantity.
Error message extract from SAP system. Copyright SAP SE.
RM769
- You are not allowed to change partially confirmed planned order &1 ?The SAP error message RM769, "You are not allowed to change partially confirmed planned order &1," typically occurs when you attempt to modify a planned order that has already been partially confirmed. This restriction is in place to maintain the integrity of the production planning process.
Cause:
- Partial Confirmation: The planned order has been partially confirmed, meaning that some of the components or operations have been processed, and the system does not allow changes to avoid inconsistencies.
- Authorization Issues: The user may not have the necessary authorizations to change a partially confirmed order.
- System Settings: Certain configuration settings in the system may restrict changes to confirmed orders.
Solution:
- Complete Confirmation: If you need to make changes, you may first need to complete the confirmation of the planned order. This can be done by confirming the remaining quantities or operations.
- Revoke Confirmation: If applicable, you can revoke the confirmation of the planned order. This will allow you to make changes, but be cautious as this may affect production planning and inventory.
- Use transaction code CO15 to revoke confirmation.
- Check Authorizations: Ensure that you have the necessary authorizations to modify planned orders. If not, contact your SAP security administrator to request the required permissions.
- Consult Configuration: If the issue persists, consult with your SAP configuration team to review the settings related to planned order confirmations and any restrictions that may be in place.
Related Information:
If the problem continues after trying the above solutions, it may be beneficial to engage with your SAP support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
RM765
Item cannot be deleted (non-cumulated backlogs)
What causes this issue? The setting "Non-cumulated backlogs from backflushing" is active for the assembly of the item to be deleted. You ca...
RM764
At least one item was not deleted due to non-cumulated backlogs
What causes this issue? You selected at least one item for which individual reprocessing records (non-cumulated backlogs from backflushing) were crea...
RM770
Cancellation not poss. because decoupled conf. already post-executed
What causes this issue? You cannot reverse this backflush as the subsequent, separate backflush has already been carried out. Two reasons exist for t...
RM771
Cancellation not possible because RP document &1 not cancellable
What causes this issue? The reporting point for which the backflush was carried out was deleted by a routing change. Therefore, you cannot reverse th...
Click on this link to search all SAP messages.