Message type: E = Error
Message class: PSZ1 - PS Payment Planning: Function Group KPP_PSZ
Message number: 009
Message text: Status forbids payment planning for WBS element &1
The current status of WBS element &V1& prohibits transaction
<ZK>FIPL Payment Planning</>.
WBS element &V1& is not processed.
Check the status of the WBS element and change it as required.
Error message extract from SAP system. Copyright SAP SE.
The SAP error message PSZ1009, which states "Status forbids payment planning for WBS element &1," typically occurs in the context of Project System (PS) when you attempt to plan payments for a Work Breakdown Structure (WBS) element that is in a status that does not allow for payment planning.
Cause: The error is usually caused by one of the following reasons: WBS Element Status: The WBS element has a status that prohibits payment planning. This could be due to the WBS being in a closed status or a status that restricts further financial transactions. Project Lifecycle: The project may be in a phase where payment planning is not allowed, such as after project completion or if the project is flagged for deletion. Configuration Settings: The system configuration may have specific settings that restrict payment planning based on the status of the WBS element.
Solution: To resolve this error, you can take the following steps: Check WBS Element Status: Use
Get instant SAP help. Sign up for our Free Essentials Plan.
PSZ1008 See error log
What causes this issue? An error has occurred.System Response INCLUDE NA_ALLG_NOVERARBEITUNG OBJECT DOKU ID TXHow to fix this error? View the error...
PSZ1007 WBS element &1 is not assigned to an FM area
What causes this issue? WBS element &V1& is assigned to company code &V2&. This company code is not assgined to an FM area.System Res...
PSZ1010 Lock on objects
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PSZ1011 No commitment items exist for FM area &1
What causes this issue? No suitable commitment items have been maintained for manual payment planning in FM area &V1&.System Response INCLUD...