Do you have any question about this error?
Message type: E = Error
Message class: PPEFLO - Messages for iPPE Application Object FLO
Message number: 406
Message text: Standard path indicator not clear for &1 &2. Alternative &3 selected
&V1& &V2& is a <DS:GLOS.B12975DA5FD6D411BCBA0800060D9C68>multiple work
center.</> In the case of multiple work centers, exactly one of the
alternative work centers must be selected as the standard path along
the production line. This standard path is relevant for planning.
For &V1& &V2&, more than one of the alternatives has been selected as
the standard path. This means that a unique selection cannot be made,
which is necessary for planning.
The system has selected the alternative &V3& as the standard path. This
selection was made on the basis of the way all the alternatives of &V1&
&V2& that have been selected as the standard path are sorted.
Indicate which alternative of &V1& &V2& is the unique and correct
standard alternative.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
PPEFLO406
- Standard path indicator not clear for &1 &2. Alternative &3 selected ?The SAP error message PPEFLO406 indicates that there is an issue with the standard path indicator not being clear for a specific production order or process order. This error typically arises in the context of production planning and execution, particularly when dealing with alternative paths in the production process.
Cause:
- Standard Path Indicator Not Set: The standard path indicator for the specified order (e.g., &1 for the order number and &2 for the operation) is not properly defined or is ambiguous.
- Alternative Path Selected: The system has detected that an alternative path (&3) has been selected, but the standard path is not clear, which can lead to confusion in the production process.
- Configuration Issues: There may be configuration issues in the routing or production version that prevent the system from determining the correct standard path.
- Master Data Issues: Problems with the master data, such as incorrect routing or production versions, can also lead to this error.
Solution:
Check Routing and Production Version:
- Verify that the routing for the material in question is correctly defined and that the standard path indicator is set appropriately.
- Ensure that the production version is correctly assigned to the material and that it includes the necessary operations.
Clear Standard Path Indicator:
- If the standard path indicator is not needed, you may need to clear it or set it correctly in the routing or production version.
Review Alternative Paths:
- If alternative paths are being used, ensure that they are correctly configured and that the system can clearly identify which path to follow.
Consult Documentation:
- Review SAP documentation or help resources related to production planning and execution to understand the implications of the standard path indicator and how to manage it.
SAP Notes and Support:
- Check for any relevant SAP Notes that may address this specific error message. Sometimes, SAP releases notes that provide fixes or workarounds for known issues.
Contact SAP Support:
- If the issue persists after checking the above points, consider reaching out to SAP support for further assistance. They may provide insights specific to your system configuration.
Related Information:
By following these steps, you should be able to identify and resolve the issue related to the PPEFLO406 error message in SAP.
Get instant SAP help. Start your 7-day free trial now.
PPEFLO405
Standard path indicator is missing for &1 &2. Alternative &3 selected
What causes this issue? &V1& &V2& is a <DS:GLOS.B12975DA5FD6D411BCBA0800060D9C68>multiple work center</>. In the case of ...
PPEFLO404
Line explosion in execution mode is not allowed for &1 &2
What causes this issue? You wish to explode a line structure with additional data for Logistics Execution. However, such an explosion is not possible...
PPEFLO407
In line balance relatshp &1 to &2, &1 is not within line bal. line (&3)
What causes this issue? In the line balance relationship &V1& to &V2& from line balance &V3&, &V1& is not part of the...
PPEFLO408
Colored material &1 does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.