How To Fix PPEACT109 - No capacity requirements maintained at &1 &2 for resource &3


PPEACT109 - Overview

  • Message type: E = Error

  • Message class: PPEACT - Messages for iPPE ACT Application (Activities)

  • Message number: 109

  • Message text: No capacity requirements maintained at &1 &2 for resource &3

  • Show details Hide details
  • What causes this issue?

    For resource &V3& to be included in planning in SAP APO, you must enter
    capacity requirements. However, no capacity requirements have been
    specified at &V1& &V2& for the resource.

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    System Response

    How to fix this error?

    Maintain the capacity requirements with the relevant unit of measure for
    the resource &V3& at &V1& &V2&.

    Procedure for System Administrators


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message PPEACT109 - No capacity requirements maintained at &1 &2 for resource &3 ?
    The SAP error message PPEACT109 indicates that there are no capacity requirements maintained for a specific resource in the context of production planning or capacity planning. This error typically arises when trying to execute a production order, process order, or similar activities where capacity planning is involved.
    
    Cause: The error occurs due to one or more of the following reasons: Missing Capacity Planning Data: The resource (work center or production line) does not have any capacity requirements defined for the specified period. Incorrect Configuration: The configuration for the resource may not be set up correctly, leading to a lack of capacity data. Resource Not Assigned: The resource may not be assigned to the relevant production process or order. Date Range Issues: The date range for the capacity requirements may not cover the period for which the production order is being processed.
    Solution: To resolve the PPEACT109 error, you can take the following steps: Check Capacity Planning Data: Go to the

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author