Message type: E = Error
Message class: PPEACT - Messages for iPPE ACT Application (Activities)
Message number: 108
Message text: Scheduling data is incomplete for &1 &2
For an activity to be considered for planning in SAP APO, at least one
standard time must be maintained at the activity mode.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Enter at least one standard time (with corresponding unit) at &V1& &V2&.
Error message extract from SAP system. Copyright SAP SE.
PPEACT108
- Scheduling data is incomplete for &1 &2 ?The SAP error message PPEACT108 indicates that the scheduling data is incomplete for a specific production order or process order. This error typically arises in the context of production planning and execution, particularly when the system is unable to find all the necessary scheduling information to proceed with the operation. Cause The error can be caused by several factors, including: Missing Scheduling Data: The production order or process order may not have all the required scheduling data filled in, such as start and finish dates, or the necessary operations may not be defined. Incomplete Master Data: The master data for the materials, routing, or work centers may be incomplete or incorrectly configured, leading to missing scheduling information.
Configuration Issues: There may be issues with the configuration of the production planning module, such as missing settings in the production version or planning strategy. Status of the Order: The order may be in a status that does not
Get instant SAP help. Sign up for our Free Essentials Plan.
PPEACT107
No primary resource is maintained for &1 &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
OIUCI536
Check Amount must be > 0
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PPEACT109
No capacity requirements maintained at &1 &2 for resource &3
What causes this issue? For resource &V3& to be included in planning in SAP APO, you must enter capacity requirements. However, no capacity r...
PPEACT110
Type 'setup/tear down' is no longer supported for &1 &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.