Do you have any question about this error?
Message type: E = Error
Message class: ORB - Project-Related Incoming Orders/Open Orders
Message number: 500
Message text: No strategy maintained for project profile &1
You must define a strategy in the project profile so that settlement
rules can be generated automatically. There is no strategy in project
profile &V1&.
Current object not processed.
Go to the Project System IMG and assign a strategy to project profile
&V1&.
Error message extract from SAP system. Copyright SAP SE.
ORB500
- No strategy maintained for project profile &1 ?The SAP error message ORB500, which states "No strategy maintained for project profile &1," typically occurs in the context of project management within SAP, particularly when dealing with project profiles in the Project System (PS) module. This error indicates that there is no valid strategy defined for the specified project profile, which is necessary for the system to determine how to handle certain processes related to that project.
Cause:
- Missing Strategy: The project profile specified in the error message does not have an associated strategy defined in the system.
- Configuration Issues: The project profile may not be properly configured in the system, leading to the absence of a strategy.
- Incorrect Project Profile: The project profile being referenced may be incorrect or not applicable for the current project.
Solution:
To resolve the ORB500 error, you can follow these steps:
Check Project Profile Configuration:
- Go to the transaction code
OPRJ
(Project Profile) in SAP.- Verify that the project profile specified in the error message exists and is correctly configured.
Maintain Strategy:
- If the project profile exists but does not have a strategy, you need to maintain a strategy for it.
- Use transaction code
OPR1
(Define Project Profile) to define or modify the project profile and assign a strategy.Assign a Valid Strategy:
- Ensure that a valid strategy is assigned to the project profile. This can involve linking it to a specific planning or execution strategy that fits the project requirements.
Check for Customizations:
- If your organization has custom strategies or profiles, ensure that they are correctly set up and that the project profile is linked to the appropriate custom strategy.
Consult Documentation:
- Review any relevant documentation or guidelines provided by your organization regarding project profiles and strategies in SAP.
Testing:
- After making the necessary changes, test the project creation or processing again to ensure that the error is resolved.
Related Information:
Transaction Codes:
OPRJ
: Project Profile ConfigurationOPR1
: Define Project ProfileCJ20N
: Project Builder (to view and manage projects)SAP Notes: Check SAP Notes for any known issues or additional guidance related to the ORB500 error.
User Roles: Ensure that you have the necessary authorizations to make changes to project profiles and strategies in SAP.
By following these steps, you should be able to resolve the ORB500 error and ensure that your project profiles are correctly configured with the necessary strategies.
Get instant SAP help. Start your 7-day free trial now.
ORB402
The only permitted acct asst cat for this object type is "No receiver"
What causes this issue? The current settings should reference objects which do not allow account assignment with actual costs or actual revenues. Set...
ORB401
Specify a settlement profile
What causes this issue? To have the system generate the settlement rule automatically, you must specify at least one settlement profile. This is nece...
ORB501
Object not processed because of errors
What causes this issue? Errors have occurred during processing of the current object. For details, see the messages for this object.System Response ...
ORB502
The settlement parameters cannot be changed
What causes this issue? Settlement profile &V2& is assigned to the current object. However, the system determined profile &V1& from t...
Click on this link to search all SAP messages.