Do you have any question about this error?
Message type: E = Error
Message class: MPE_SFMASTERISSU_MSG -
Message number: 002
Message text: Production version is not valid on end date of planned order
The production version of the planned order is not valid on the planned
order end date.
MRP only selects a production version if the production version is valid
on the planned order end date.
Possible reasons for this situation include:
?,,The validity period of the production version was changed after
creating the planned order.
?,,The planned order was changed by custom code or external interfaces.
Conversion of the planned order to a production order will not change
the production version.
Explode the planned order BOM or reschedule the planned order.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MPE_SFMASTERISSU_MSG002
- Production version is not valid on end date of planned order ?The SAP error message MPE_SFMASTERISSU_MSG002 indicates that the production version specified for a planned order is not valid on the end date of that planned order. This typically occurs when the production version has a validity period that does not encompass the date of the planned order.
Cause:
- Invalid Production Version: The production version assigned to the planned order has a validity period that does not include the planned order's end date.
- Master Data Issues: The production version may have been changed or deleted, or the validity dates may not have been updated correctly in the master data.
- Configuration Issues: There may be configuration settings in the material master or production version that are not aligned with the planned order requirements.
Solution:
Check Production Version Validity:
- Go to the material master (transaction code MM03) and check the production version assigned to the material.
- Verify the validity dates of the production version to ensure they cover the planned order's end date.
Update Production Version:
- If the production version is not valid, you may need to create a new production version or adjust the existing one to extend its validity period to include the planned order's end date.
Adjust Planned Order Dates:
- If possible, adjust the planned order's end date to fall within the validity period of the existing production version.
Review Master Data:
- Ensure that all relevant master data (material master, BOM, routing) is correctly maintained and that there are no inconsistencies.
Consult Documentation:
- Review SAP documentation or consult with your SAP support team for any specific configurations or settings that may affect production version validity.
Related Information:
By following these steps, you should be able to resolve the error and ensure that your planned orders are correctly aligned with valid production versions.
Get instant SAP help. Start your 7-day free trial now.
MPE_SFMASTERISSU_MSG001
Date-effective BOM and routing used for production execution
What causes this issue? Shop floor BOM and routing are not version controlled.System Response Date-effective BOM and routing are used for production...
MPE_SFMASTERISSU_MSG000
Planned order has no production version
What causes this issue? The planned order has no production version.System Response MRP and production order creation find BOM and routing only thro...
MPE_SFMASTERISSU_MSG003
Production version does not cover quantity of planned order
What causes this issue? The production version of the planned order is not valid for the planned order quantity. MRP only selects a production versio...
MPE_SFMASTERISSU_MSG004
Valid shop floor BOM and routing version is not available
What causes this issue? There is no shop floor BOM and routing version valid on the planned order explosion date.System Response The system will not...
Click on this link to search all SAP messages.