Do you have any question about this error?
Message type: E = Error
Message class: MPE_INSTALLATION_MSG -
Message number: 020
Message text: Different networks of same project have different parameter eff. value
You have specified different parameter effectivity values for the
networks of the same WBS element.
MRP cannot separate demand that has different parameter effectivity
values. MRP can separate demand for different end-item units and explode
the BOM correctly only if demand with different parameter effectivity
values also has different WBS elements.
Change the model/unit of the network using transaction <AB>CJ20N</>.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MPE_INSTALLATION_MSG020
- Different networks of same project have different parameter eff. value ?The SAP error message MPE_INSTALLATION_MSG020 indicates that there is a discrepancy in the effective parameter values across different networks within the same project. This typically occurs in the context of project management or network planning in SAP, where different networks (or activities) are expected to have consistent parameter settings.
Cause:
The error arises when:
To resolve this error, you can follow these steps:
Identify the Networks: Determine which networks are causing the issue. You can do this by reviewing the project structure and the parameters assigned to each network.
Check Parameter Settings: For each network, check the effective parameter values. You can do this by navigating to the network details in the project management module.
Standardize Parameter Values: Ensure that the effective parameter values are consistent across all networks. You may need to:
CJ20N
(Project Builder) to edit the project and its networks.Review Configuration: If the issue persists, review the configuration settings in the project management module to ensure that there are no underlying issues causing the discrepancies.
Test Changes: After making the necessary adjustments, test the changes to ensure that the error message no longer appears.
Documentation: Document the changes made for future reference and to help prevent similar issues from occurring.
CJ20N
(Project Builder), CJI3
(Project Actual Line Items), and CJ02
(Change Work Breakdown Structure).By following these steps, you should be able to resolve the error and ensure consistency across your project networks.
Get instant SAP help. Start your 7-day free trial now.
MPE_INSTALLATION_MSG019
Inconsistent parameter effectivity
What causes this issue? The network?s parameter effectivity was changed after the previous BOM explosion. This could have been an attempt to reassign...
MPE_INSTALLATION_MSG018
Network activity not yet released
What causes this issue? Production planning has not yet been completed.System Response Production planners confirm the completion of production plan...
MPE_INSTALLATION_MSG021
The same parameter eff. value is used in different projects
What causes this issue? You accidentally used the same model-unit for different networks.System Response In complex assembly, parameter effectivity ...
MPE_INSTALLATION_MSG022
BOM item has no reference point
What causes this issue? A reference point is not maintained in the BOM item.System Response Reference points are used to assign BOM items to network...
Click on this link to search all SAP messages.