Message type: E = Error
Message class: MMRP01 - Rapid Planning Matrix
Message number: 224
Message text: Backflush not possible as explosion has not been carried out (start RPM)
The order is in a long-term planning matrix.
Orders in long-term planning matrices cannot be backflushed.
The order cannot be backflushed until the order lies within the
detailed scheduling horizon for the planning matrix.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MMRP01224
- Backflush not possible as explosion has not been carried out (start RPM) ?The SAP error message MMRP01224 indicates that a backflush operation cannot be performed because the explosion of the bill of materials (BOM) has not been carried out. This typically occurs in the context of production orders or process orders where components need to be allocated before backflushing can take place.
Cause:
- BOM Explosion Not Executed: The primary reason for this error is that the system has not processed the BOM explosion for the production order. The explosion is necessary to determine which components are required for the production process.
- Order Status: The production order may not be in the correct status to allow for backflushing. For example, if the order is not released or is in a status that does not permit backflush, this error can occur.
- Configuration Issues: There may be configuration settings in the system that prevent the explosion from being executed properly.
- Missing Components: If the components required for the production order are not available or not defined in the BOM, the explosion may not occur.
Solution:
Execute BOM Explosion: Ensure that the BOM explosion has been executed for the production order. This can typically be done by:
- Going to the production order and executing the explosion manually if needed.
- Checking the order status and ensuring it is released.
Check Order Status: Verify that the production order is in a status that allows for backflushing. The order should be released and not in a status that prevents further processing.
Review BOM Configuration: Check the configuration of the BOM to ensure that it is correctly set up and that all components are defined. Make sure that the BOM is valid for the material and the production order.
Check Component Availability: Ensure that all components required for the production order are available and correctly defined in the system.
Consult Documentation: If the issue persists, consult SAP documentation or your internal SAP support team for further troubleshooting steps specific to your configuration.
Related Information:
By following these steps, you should be able to resolve the MMRP01224 error and successfully perform the backflush operation.
Get instant SAP help. Sign up for our Free Essentials Plan.
MMRP01223
Fixing/ATP not possible because explosion not yet carried out (start RPM)
What causes this issue? The order is in a long-term planning matrix.System Response Orders in long-term planning matrices cannot be fixed or checked...
MMRP01222
Order BOM is not available as it has not yet been exploded (start RPM)
What causes this issue? The order is in a long-term planning matrix. The settings for the finished product mean that the crosses are to be deleted fr...
MMRP01225
Component variant &1 cannot be changed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MMRP01226
Job for calculating the &1 terminated. Attempts remaining: &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...