Message type: E = Error
Message class: MMRP01 - Rapid Planning Matrix
Message number: 222
Message text: Order BOM is not available as it has not yet been exploded (start RPM)
The order is in a long-term planning matrix. The settings for the
finished product mean that the crosses are to be deleted from the
long-term planning matrix when the component requirements have been
determined.
The system cannot display an order BOM for this order.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MMRP01222
- Order BOM is not available as it has not yet been exploded (start RPM) ?The SAP error message MMRP01222 indicates that the Bill of Materials (BOM) for a production order is not available because it has not yet been exploded. This typically occurs in the context of production planning and execution, where the system needs to access the detailed components of a BOM to proceed with production activities.
Cause:
- BOM Not Exploded: The primary reason for this error is that the BOM for the production order has not been exploded. This means that the system has not yet generated the detailed list of components required for the production order.
- Order Status: The production order may be in a status that does not allow BOM explosion, such as "Created" or "Released" without the necessary steps being completed.
- Missing Master Data: There may be missing or incorrect master data related to the material, such as the BOM itself not being defined or not being valid for the specific order.
- Scheduling Issues: If the order is scheduled for a time that is not valid or if there are issues with the routing, the BOM may not be exploded.
Solution:
- Explode the BOM: You can manually explode the BOM for the production order. This can typically be done through transaction codes like
CO01
(Create Production Order) orCO02
(Change Production Order). Ensure that the order is in a status that allows for BOM explosion.- Check BOM Validity: Verify that the BOM exists for the material and is valid for the specific plant and production version. You can check this using transaction
CS03
(Display BOM).- Check Order Status: Ensure that the production order is in a status that allows for BOM explosion. If necessary, change the status of the order to allow for this process.
- Re-schedule the Order: If the order is not scheduled correctly, you may need to re-schedule it to a valid time frame.
- Run MRP: If the BOM is not exploded due to MRP (Material Requirements Planning) not being run, you may need to execute MRP for the relevant materials to ensure that the BOM is exploded and components are available.
Related Information:
CS03
: Display BOMCO01
: Create Production OrderCO02
: Change Production OrderMD01
: MRP RunIf the issue persists after following these steps, it may be beneficial to consult with your SAP support team or refer to SAP documentation for further troubleshooting.
Get instant SAP help. Start your 7-day free trial now.
MMRP01221
Selection with order reference not possible for aggregated requirements
What causes this issue? You tried to enter a selection criterion with an order reference (for example, finished product, order number, start date, ex...
MMRP01220
Internal error: More than one KNNUM with prio 0 found for KNOBJ &2
What causes this issue? Several KNNUMs have been found with priority 0 for the KNOBJ &V2& for component variant &V1&.System Response ...
MMRP01223
Fixing/ATP not possible because explosion not yet carried out (start RPM)
What causes this issue? The order is in a long-term planning matrix.System Response Orders in long-term planning matrices cannot be fixed or checked...
MMRP01224
Backflush not possible as explosion has not been carried out (start RPM)
What causes this issue? The order is in a long-term planning matrix.System Response Orders in long-term planning matrices cannot be backflushed.How ...
Click on this link to search all SAP messages.