How To Fix MM248 - The planning strategy group & does not exist


SAP Error Message - Details

  • Message type: E = Error

  • Message class: MM - Messages for material master maintenance and Customizing

  • Message number: 248

  • Message text: The planning strategy group & does not exist

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message MM248 - The planning strategy group & does not exist ?

    The SAP error message MM248, which states "The planning strategy group & does not exist," typically occurs in the context of materials management and production planning. This error indicates that the system is unable to find a specified planning strategy group in the configuration.

    Cause:

    1. Missing Configuration: The planning strategy group specified in the material master or in the planning settings does not exist in the system. This could be due to a typo, or the group may not have been created yet.
    2. Incorrect Material Master Data: The material master record may reference a planning strategy group that has not been defined or has been deleted.
    3. Transport Issues: If the planning strategy group was recently created or modified in a different environment (like development or quality), it may not have been transported to the production environment.

    Solution:

    1. Check Planning Strategy Group:

      • Go to the transaction code SPRO (Customizing) and navigate to the relevant section for planning strategy groups.
      • Verify if the planning strategy group exists. If it does not, you may need to create it.
    2. Create/Modify Planning Strategy Group:

      • If the planning strategy group is missing, you can create it by navigating to:
        • Logistics > Production > Production Planning > Master Data > Planning Strategy > Define Planning Strategies.
      • Ensure that the planning strategy group is correctly defined according to your business requirements.
    3. Check Material Master:

      • Use transaction code MM03 to display the material master record and check the planning strategy group assigned to the material.
      • If the planning strategy group is incorrect, you can change it using transaction code MM02.
    4. Transport Issues:

      • If the planning strategy group was created in a different environment, ensure that the transport request containing the new configuration has been successfully imported into the production environment.
    5. Consult Documentation: If you are unsure about the planning strategy groups and their implications, refer to SAP documentation or consult with your SAP functional consultant.

    Related Information:

    • Planning Strategies: Planning strategies in SAP define how the system should plan for materials, including make-to-stock, make-to-order, and other strategies.
    • Transaction Codes: Familiarize yourself with relevant transaction codes such as MM01 (Create Material), MM02 (Change Material), MM03 (Display Material), and SPRO (Customizing).
    • SAP Notes: Check SAP Notes for any known issues or additional guidance related to the error message MM248.

    By following these steps, you should be able to resolve the error and ensure that the planning strategy group is correctly configured in your SAP system.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth