How To Fix MD485 - Scheduling terminated, see log


SAP Error Message - Details

  • Message type: E = Error

  • Message class: MD - Material Requirements Planning (MRP)

  • Message number: 485

  • Message text: Scheduling terminated, see log

  • Show details Hide details
  • What causes this issue?

    When scheduling, an error occurred that was the reason for the
    termination, for example, the order quantity could not be converted
    into the unit of measure of the rouing. An error message was recorded
    in the scheduling log.

    System Response

    Planned orders were not scheduled and no capacity requirements were
    created.

    How to fix this error?

    Display the scheduling log. This log is not saved in the system so you
    have to schedule the planned order first so that the system can record
    it.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message MD485 - Scheduling terminated, see log ?

    The SAP error message MD485 ("Scheduling terminated, see log") typically occurs during the planning or scheduling process in SAP, particularly in the context of Material Requirements Planning (MRP) or Production Planning (PP). This error indicates that the scheduling process could not be completed successfully, and further details can be found in the log.

    Causes:

    1. Data Issues: Missing or incorrect master data (e.g., material master, BOM, routing) can lead to scheduling failures.
    2. Capacity Constraints: If there are insufficient resources (e.g., work centers, machines) to meet the production requirements, scheduling may be terminated.
    3. Configuration Errors: Incorrect settings in the planning parameters or MRP settings can cause scheduling issues.
    4. Stock Levels: Inadequate stock levels or incorrect stock status (e.g., blocked stock) can lead to scheduling problems.
    5. Dependencies and Constraints: If there are dependencies or constraints that cannot be resolved, the scheduling process may fail.

    Solutions:

    1. Check the Log: The first step is to check the detailed log for the specific error messages. You can find the log in transaction code MD04 (Stock/Requirements List) or MD05 (MRP List).
    2. Review Master Data: Ensure that all relevant master data (material master, BOM, routing) is complete and accurate.
    3. Analyze Capacity: Check the capacity of work centers and ensure that they are sufficient to handle the planned production.
    4. Adjust Planning Parameters: Review and adjust MRP parameters and settings to ensure they are configured correctly.
    5. Stock Review: Verify stock levels and ensure that there are no issues with stock status that could affect scheduling.
    6. Run MRP Again: After addressing the issues, you may need to rerun the MRP process to see if the problem is resolved.

    Related Information:

    • Transaction Codes: Familiarize yourself with relevant transaction codes such as MD04 (Stock/Requirements List), MD05 (MRP List), and MD02 (MRP Run).
    • SAP Notes: Check SAP Notes for any known issues or patches related to the error message MD485.
    • Documentation: Review SAP documentation on MRP and PP for best practices and troubleshooting steps.
    • User Forums: Engage with SAP community forums or user groups for additional insights and solutions from other users who may have encountered similar issues.

    By following these steps, you should be able to identify the root cause of the MD485 error and implement the necessary solutions to resolve it.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author