Do you have any question about this error?
Message type: E = Error
Message class: KP - CO-OM Planning
Message number: 275
Message text: &: Manually-set activity price varies.
You set a manual activity price in &V1&. Simultaneously, an annual
price is calculated for version &V3&, meaning that the activity price
for all periods is identical. This is not the case for the manual
activity price in &V1&.
Activity price calculation uses the price in period &V4& for all
periods. Since this is a serious error, however, the calculation
results are not posted.
Change the activity price in &V1&, or set the price to iterative so
that an annual activity price is calculated and set for all periods.
Error message extract from SAP system. Copyright SAP SE.
KP275
- &: Manually-set activity price varies. ?The SAP error message KP275: "Manually-set activity price varies" typically occurs in the context of controlling (CO) when there is a discrepancy between the manually set activity price and the expected or standard activity price in the system. This can happen during various processes, such as when you are trying to settle costs or when performing planning activities.
Cause:
- Manual Price Entry: The activity price has been manually entered in a way that does not match the price defined in the system for that activity type.
- Price Variance: There may be a difference between the planned price and the actual price for the activity type.
- Configuration Issues: There could be issues with the configuration of the activity types or cost centers in the controlling module.
- Data Entry Errors: Mistakes during data entry can lead to discrepancies in the activity price.
Solution:
- Check Activity Price: Verify the manually set activity price against the standard or planned price in the system. You can do this by navigating to the relevant activity type in the controlling area.
- Adjust Prices: If the manually set price is incorrect, adjust it to match the expected price. This can be done in the transaction code KP26 (Change Activity Type Prices).
- Review Configuration: Ensure that the configuration for the activity types and cost centers is correct. Check if the activity types are properly defined and that the price settings are consistent.
- Consult Documentation: Review any relevant documentation or guidelines for setting activity prices to ensure compliance with internal processes.
- Re-run Processes: After making the necessary adjustments, re-run the process that triggered the error to see if it resolves the issue.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in SAP Controlling.
Get instant SAP help. Start your 7-day free trial now.
KP274
&: Activity is zero.
What causes this issue? Planning of activity quantities for &V1& in period(s) &V3& is not reconciled. Plan activity for &V1& ...
KP273
&: Activity is less than scheduled.
What causes this issue? Planning of activity quantities for &V1& in period(s) &V3& is not reconciled. Plan activity is smaller than t...
KP276
&: Costs planned or posted despite zero activity
What causes this issue? Plan activity and posted activity for &V1& are both 0. Nevertheless, costs were planned or posted.System Response Th...
KP277
&: Activity relationship with zero activity.
Plan activity for &V1& is 0. Nevertheless, activity input was planned for &V2&.System Response The activity price for this activity ...
Click on this link to search all SAP messages.