Do you have any question about this error?
Message type: E = Error
Message class: KP - CO-OM Planning
Message number: 272
Message text: Sender in an activity relationship has no activity.
In the iterative activity price calculation framework, a relationship
between &V1& and &V2& was determined due to planning/posting of an
activity reference (activity-dependent or activity-independent).
However, only one activity record without an activity quantity was
found for the sender.
The activity relationship is rejected.
Inform your system administrator. There are faulty data records in the
transaction data files.
Error message extract from SAP system. Copyright SAP SE.
KP272
- Sender in an activity relationship has no activity. ?The SAP error message KP272 ("Sender in an activity relationship has no activity") typically occurs in the context of project management or production planning when there is an issue with the configuration of activity relationships in a network or project. This error indicates that the sender activity specified in the relationship does not exist or is not defined correctly.
Cause:
- Missing Activity: The sender activity referenced in the activity relationship does not exist in the project or network.
- Incorrect Activity Number: The activity number may have been entered incorrectly or may have been deleted.
- Inactive Activity: The activity might be inactive or not properly defined in the system.
- Network Structure Issues: There may be issues with the overall structure of the network or project that prevent the system from recognizing the activity.
Solution:
- Check Activity Existence: Verify that the sender activity exists in the project or network. You can do this by navigating to the relevant project or network and checking the list of activities.
- Correct Activity Number: Ensure that the correct activity number is being used in the relationship. If it has been changed or deleted, update the relationship accordingly.
- Activate Activity: If the activity is inactive, activate it or ensure it is properly defined in the system.
- Review Activity Relationships: Check the activity relationships to ensure they are set up correctly. You may need to delete and recreate the relationship if it is incorrectly configured.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing activities and relationships in your version of SAP.
Related Information:
CJ20N
(Project Builder) or CN41
(Network Overview) to view and manage project activities and relationships.If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a technical consultant who can provide more in-depth assistance.
Get instant SAP help. Start your 7-day free trial now.
KP271
Receiver in a plan activity allocation was not found.
What causes this issue? In the iterative activity price calculation framework, a relationship between &V1& and &V2& was determined du...
KP270
Activity price calculation without activity not possible.
What causes this issue? A program error occurred during activity price calculation. The activity price for &V1& could not be determined becau...
KP273
&: Activity is less than scheduled.
What causes this issue? Planning of activity quantities for &V1& in period(s) &V3& is not reconciled. Plan activity is smaller than t...
KP274
&: Activity is zero.
What causes this issue? Planning of activity quantities for &V1& in period(s) &V3& is not reconciled. Plan activity for &V1& ...