How To Fix KP272 - Sender in an activity relationship has no activity.


SAP Error Message - Details

  • Message type: E = Error

  • Message class: KP - CO-OM Planning

  • Message number: 272

  • Message text: Sender in an activity relationship has no activity.

  • Show details Hide details
  • What causes this issue?

    In the iterative activity price calculation framework, a relationship
    between &V1& and &V2& was determined due to planning/posting of an
    activity reference (activity-dependent or activity-independent).
    However, only one activity record without an activity quantity was
    found for the sender.

    System Response

    The activity relationship is rejected.

    How to fix this error?

    Inform your system administrator. There are faulty data records in the
    transaction data files.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message KP272 - Sender in an activity relationship has no activity. ?

    The SAP error message KP272 ("Sender in an activity relationship has no activity") typically occurs in the context of project management or production planning when there is an issue with the configuration of activity relationships in a network or project. This error indicates that the sender activity specified in the relationship does not exist or is not defined correctly.

    Cause:

    1. Missing Activity: The sender activity referenced in the activity relationship does not exist in the project or network.
    2. Incorrect Activity Number: The activity number may have been entered incorrectly or may have been deleted.
    3. Inactive Activity: The activity might be inactive or not properly defined in the system.
    4. Network Structure Issues: There may be issues with the overall structure of the network or project that prevent the system from recognizing the activity.

    Solution:

    1. Check Activity Existence: Verify that the sender activity exists in the project or network. You can do this by navigating to the relevant project or network and checking the list of activities.
    2. Correct Activity Number: Ensure that the correct activity number is being used in the relationship. If it has been changed or deleted, update the relationship accordingly.
    3. Activate Activity: If the activity is inactive, activate it or ensure it is properly defined in the system.
    4. Review Activity Relationships: Check the activity relationships to ensure they are set up correctly. You may need to delete and recreate the relationship if it is incorrectly configured.
    5. Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing activities and relationships in your version of SAP.

    Related Information:

    • Transaction Codes: You may use transaction codes like CJ20N (Project Builder) or CN41 (Network Overview) to view and manage project activities and relationships.
    • SAP Notes: Check for any relevant SAP Notes that may address known issues or provide additional troubleshooting steps.
    • User Authorization: Ensure that you have the necessary authorizations to view and modify activities and relationships in the project.

    If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a technical consultant who can provide more in-depth assistance.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant