Message type: E = Error
Message class: KJ - Cost Object Controlling for Make-to-Order Production
Message number: 135
Message text: Run schedule header is assigned to sales order or project
The work in process for this run schedule header is calculated in
<DS:GLOS.results_analysis>results analysis</> for the sales order or
project.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
KJ135
- Run schedule header is assigned to sales order or project ?The SAP error message KJ135 indicates that a run schedule header (RSH) is assigned to a sales order or project, which prevents certain operations from being performed. This error typically arises in the context of production planning and control, particularly when dealing with run schedules in the context of production orders or sales orders.
Cause:
The error occurs when:
To resolve the KJ135 error, you can take the following steps:
Check Assignment: Verify the assignment of the run schedule header to the sales order or project. You can do this by navigating to the relevant transaction in SAP (e.g., COHV, CO02) and checking the details of the RSH.
Unassign or Change Assignment: If the RSH needs to be modified or deleted, you may need to unassign it from the sales order or project. This can typically be done in the production order or sales order management screens.
Review Dependencies: Ensure that there are no dependencies or processes that are currently using the RSH. If there are, you may need to complete or cancel those processes before making changes.
Consult Documentation: Refer to SAP documentation or help files for specific instructions related to your version of SAP, as the steps may vary slightly depending on the configuration and version.
Contact Support: If you are unable to resolve the issue, consider reaching out to your SAP support team or consulting with an SAP expert who can provide more tailored assistance.
By following these steps, you should be able to identify the cause of the KJ135 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
KJ134
Material &: active cost estimate has no cost element plan
What causes this issue? You are calculating work in process using the confirmed yield and the planned costs for the operations carried out up to now....
KJ133
Run schedule header with multiple positions cannot be processed
What causes this issue? Run schedule headers with more than one item cannot be processed.System Response The function is not executed.How to fix thi...
KJ136
This item has a separate cost collector
What causes this issue? The run schedule header item can carry costs. <DS:GLOS.WIP_calculation>WIP calculation</> for run schedule header...
KJ137
No item -> valuation type undefined
What causes this issue? No item exists for the run schedule header.System Response <DS:GLOS.WIP_calculation>WIP calculation</> is not po...
Click on this link to search all SAP messages.