Message type: E = Error
Message class: JITOUT - Messages for JIT Outbound
Message number: 812
Message text: GR posting for SumJC &1 &2 must be done with reference to a confirmation
You want to post goods receipt for summarized JIT call &v1&, item &v2&.
In the confirmation control key in the scheduling agreement for the
summarized JIT call you have defined that goods receipt should be
carried out with reference to a confirmation.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Post the goods receipt for the summarized JIT call using Goods Receipt
Automotive (Transaction <DS:TRAN.BORGR>BORGR</>).
Error message extract from SAP system. Copyright SAP SE.
JITOUT812
- GR posting for SumJC &1 &2 must be done with reference to a confirmation ?The SAP error message JITOUT812 indicates that a Goods Receipt (GR) posting for a specific material (in this case, SumJC) must be done with reference to a confirmation. This error typically occurs in the context of Just-In-Time (JIT) delivery processes, where the system expects that a GR is linked to a production confirmation or a delivery confirmation.
Cause:
- Missing Confirmation: The most common cause of this error is that there is no confirmation available for the production order or delivery that the GR is trying to reference.
- Incorrect Document Type: The GR might be attempted without the necessary reference document type that is required for JIT processes.
- Configuration Issues: There may be configuration settings in the JIT or logistics execution areas that are not set up correctly, leading to this error.
Solution:
- Check for Confirmation: Ensure that there is a valid confirmation for the production order or delivery. You can do this by checking the production order or delivery document in the system.
- Create Confirmation: If there is no confirmation, you may need to create one. This can typically be done through transaction codes like CO15 (for production confirmations) or VL02N (for delivery confirmations).
- Use Correct Document Reference: When performing the GR, ensure that you are referencing the correct confirmation document. This may involve using the appropriate transaction code or inputting the correct reference number.
- Review Configuration: If the issue persists, review the configuration settings related to JIT in the SAP system. This may involve checking the settings in the JIT customizing (transaction SPRO) to ensure that all necessary parameters are correctly set.
- Consult Documentation: Refer to SAP documentation or help resources for specific details on the JIT process and the requirements for GR postings.
Related Information:
If the problem continues after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in logistics and JIT processes.
Get instant SAP help. Start your 7-day free trial now.
JITOUT811
No JIT calls exist for this material document
What causes this issue? You want to reverse a material document for which no JIT calls exist. At least one of the scheduling agreements has the produ...
JITOUT810
Available quantity from batch determination is too small
What causes this issue? Batch determination was carried out for material &v1& from summarized JIT call &v2& item &V3&. The av...
JITOUT813
The status of call &1 has already been updated
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
JITOUT814
Material &1 in plant &2 is not assigned to a batch class
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...