How To Fix IP415 - Planned date is in the past


SAP Error Message - Details

  • Message type: E = Error

  • Message class: IP - Messages for preventive maintenance

  • Message number: 415

  • Message text: Planned date is in the past

  • Show details Hide details


  • Self-Explanatory Message

    Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.

    To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.

    Unfortunately, there isn't any extra information in this error notice.



    What else can you do?

    First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).

    Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.

    You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.


Smart SAP Assistant

  • What is the cause and solution for SAP error message IP415 - Planned date is in the past ?

    The SAP error message IP415 ("Planned date is in the past") typically occurs in the context of maintenance planning and scheduling within the SAP system, particularly when using the Plant Maintenance (PM) or Production Planning (PP) modules. This error indicates that the planned date for a maintenance order, production order, or similar activity is set to a date that has already passed, which is not allowed by the system.

    Cause:

    1. Incorrect Date Entry: The planned start or finish date for the order or task was entered incorrectly, leading to a date that is earlier than the current system date.
    2. System Date Mismatch: The system date may not be correctly set, leading to confusion about what constitutes a "past" date.
    3. Delayed Planning: The planning process may have been delayed, resulting in the creation of orders with dates that are no longer valid.
    4. Data Migration Issues: If data was migrated from another system, it may have included outdated dates.

    Solution:

    1. Check and Update Dates: Review the planned dates for the order or task in question. Update them to a future date that is valid.

      • Navigate to the relevant transaction (e.g., IP10 for maintenance plans) and adjust the planned dates accordingly.
    2. Verify System Date: Ensure that the system date is set correctly. You can check this by using transaction code SM51 to view the system date and time.

    3. Replan Activities: If the planned date is in the past due to delays, consider replanning the activities to ensure they are scheduled appropriately.

    4. Review Data Migration: If the error is due to data migration, review the data import process to ensure that dates are correctly formatted and valid.

    5. Consult Documentation: Refer to SAP documentation or help resources for specific guidance on handling planned dates and scheduling in your version of SAP.

    Related Information:

    • Transaction Codes: Familiarize yourself with relevant transaction codes such as IP10 (Change Maintenance Plan), IP11 (Display Maintenance Plan), and IP12 (Display Maintenance Item).
    • User Roles and Authorizations: Ensure that you have the necessary permissions to change planned dates in the system.
    • SAP Notes: Check for any SAP Notes related to this error message for additional insights or patches that may address the issue.
    • Training and Support: If you are unsure about how to proceed, consider reaching out to your SAP support team or consulting with a colleague who has experience in maintenance planning.

    By addressing the root cause of the error and following the suggested solutions, you should be able to resolve the IP415 error and proceed with your planning activities in SAP.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages: