Message type: E = Error
Message class: GM - Combination manager
Message number: 069
Message text: Results analysis cost element & is not supported in sec.cost planning
The cost element &V1& is a cost element of the type order or results
analysis for projects. These cost elements are special allocation cost
elements that are used exclusively for the accrual/deferral of costs to
orders and projects. During manual planning, such cost elements cannot
be provided with values.
Cost element &V1& is not taken into account.
Error message extract from SAP system. Copyright SAP SE.
GM069
- Results analysis cost element & is not supported in sec.cost planning ?The SAP error message GM069, which states "Results analysis cost element & is not supported in sec. cost planning," typically occurs in the context of SAP's Controlling (CO) module, particularly when dealing with results analysis (RA) and secondary cost planning.
Cause: This error usually arises when: Incompatible Cost Elements: The cost element being used for results analysis is not configured to be used in secondary cost planning. In SAP, cost elements can be classified as primary or secondary, and secondary cost elements are typically used for internal allocations and not for direct postings.
Configuration Issues: The configuration settings for the cost element in question may not allow it to be used in the context of secondary cost planning. Incorrect Assignment: The cost element may be incorrectly assigned in the results analysis configuration or in the planning layout.
Solution: To resolve the GM069 error, you can take the following steps: Check Cost Element Configuration: Go to the transaction code KA03
Get instant SAP help. Sign up for our Free Essentials Plan.
GM068
Assessment cost element & is not supported in secondary cost planning
What causes this issue? Cost element &V1& is an assessment cost element. Assessment cost elements are special allocation cost elements that a...
GM067
Cost element & can only be used for activity input
What causes this issue? You have defined cost element &V1& in the planning layout or entered it on the planning initial screen. This cost ele...
GM070
The cost element category of cost element & is not supported
What causes this issue? You want to plan cost element &V1& in the manual planning. This cost element has the cost element category &V2&am...
GM071
To allocate &/&, you cannot use cost element &
What causes this issue? You want to plan the activity input from sender cost center/activity type &V1&/&V2& on a receiver. However, o...