Do you have any question about this error?
Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 251
Message text: Overwriting of the planned dates by the actual dates is not allowed
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
DPR_SHARED251
- Overwriting of the planned dates by the actual dates is not allowed ?The SAP error message DPR_SHARED251, which states "Overwriting of the planned dates by the actual dates is not allowed," typically occurs in the context of project management within SAP, particularly when dealing with project planning and actuals in the Project System (PS) or the Portfolio and Project Management (PPM) module.
Cause:
This error arises when there is an attempt to update or overwrite planned dates (such as start or finish dates) with actual dates that have already been recorded. The system is designed to prevent this action to maintain the integrity of the project data. The planned dates are meant to represent the original schedule, while actual dates reflect what has occurred. Overwriting planned dates with actual dates can lead to inconsistencies and confusion in project tracking and reporting.
Solution:
To resolve this error, consider the following steps:
Review the Data Entry: Check the entries you are trying to make. Ensure that you are not inadvertently trying to overwrite planned dates with actual dates.
Adjust Actual Dates: If you need to change the actual dates, do so without affecting the planned dates. You may need to adjust the actual dates in a way that does not conflict with the planned dates.
Use Correct Transactions: Ensure you are using the correct transaction codes for updating project data. For example, use transactions like CJ20N for project planning and CJ02 for changing project definitions.
Consult Project Management Guidelines: Review your organization's project management guidelines to understand how planned and actual dates should be handled.
Check User Authorizations: Ensure that you have the necessary authorizations to make changes to the project data. Sometimes, restrictions may be in place that prevent certain changes.
Consult SAP Notes: Look for any relevant SAP Notes or documentation that may provide additional insights or updates regarding this error message.
Contact SAP Support: If the issue persists and you cannot find a resolution, consider reaching out to SAP support for assistance. They may provide specific guidance based on your system configuration.
Related Information:
By following these steps, you should be able to address the DPR_SHARED251 error and maintain the integrity of your project data in SAP.
Get instant SAP help. Start your 7-day free trial now.
DPR_SHARED250
The duration was adjusted according to the constraint dates
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED249
Specified finish &1 is outside the validity period of calendar &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED252
Overwriting of the planned dates by the actual dates is allowed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED253
Maximum duration of 99999 days exceeded; adjust the start or end date
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.