Message type: E = Error
Message class: DPR_SHARED - Development Projects: Messages for Shared Objects
Message number: 236
Message text: &1 &2 > &3 &4: Conflict due to moved date
You have defined a constraint for the project element <(>&<)>V2& (
<(>&<)>V1&). However, this constraint shifts the project element
<(>&<)>V4& (<(>&<)>V3&) on the time line so that it overlaps
with a predecessor or successor or is before the fixed start date or
fixed finish date of the project.
<ZU>Example:</>
Two phases P1 and P2 are linked by a relationship with a <ZH>positive</>
lag. You set the <ZK>Must start on</> constraint for a task that belongs
to phase P2 and the constraint date is before the finish date of phase
P1. This causes an overlap between the phases P1 and P2.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
The system resolves this scheduling conflict by resetting the constraint
dates for the project element <(>&<)>V2& (<(>&<)>V1&).
Check the relationships for the project element <(>&<)>V4& (
<(>&<)>V3&). Adjust the relationships accordingly. If you want the
project elements to overlap, define relationships with a <ZH>negative</>
lag.
The project element <(>&<)>V4& (<(>&<)>V3&) is a phase:
Do not allow phases to overlap; the phase concept works on the basis
that phases are disjoint.
The project element <(>&<)>V4& (<(>&<)>V3&) is the project
definition:
Set the constraints on the project element <(>&<)>V4& (<(>&<)>V3
&) accordingly or adjust the constraints on the project
definition.
Error message extract from SAP system. Copyright SAP SE.
DPR_SHARED236
- &1 &2 > &3 &4: Conflict due to moved date ?The SAP error message DPR_SHARED236 indicates a conflict due to a moved date in the context of project management, particularly when dealing with project definitions, work packages, or tasks in the SAP Project System (PS) or SAP Portfolio and Project Management (PPM) modules. This error typically arises when there is a scheduling conflict due to changes in dates that affect dependencies or relationships between project elements.
Cause: The error message DPR_SHARED236 is triggered when: A date change (e.g., start date, finish date) for a project element (like a task or work package) conflicts with the dates of other related elements. The moved date violates the constraints or dependencies set between tasks, such as finish-to-start, start-to-start, or other relationships. There may be overlapping dates that are not allowed based on the project scheduling rules.
Solution: To resolve the DPR_SHARED236 error, you can take the following steps: Check Dependencies: Review the dependencies between the project elements. Ensure that the moved
Get instant SAP help. Sign up for our Free Essentials Plan.
DPR_SHARED235
Fixed finish conflicts with the end of the time frame (phase/project)
What causes this issue? A finish constraint was entered for the checklist item. The checklist that belongs to the checklist item is defined below a p...
DPR_SHARED234
Top-down scheduling was carried out
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
DPR_SHARED237
&1 &2: Calculated start is outside the specified time frame
What causes this issue? The start date for the project element &V1& &V2& that was determined using the relationships is before the ti...
DPR_SHARED238
Status of predecessor/successor does not permit relationship
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...