Do you have any question about this error?
Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 139
Message text: Order & has no requirements in the eval. period, so there is no display
Orders were selected that have no requirements in the evaluation period
or they have requirements at other work centers from those that were
selected (for example, by the overall load of a person).
Adjust the evaluation period in the time profile.
Error message extract from SAP system. Copyright SAP SE.
CY139
- Order & has no requirements in the eval. period, so there is no display ?The SAP error message CY139 indicates that there are no requirements for a specific order during the evaluation period, which means that the system cannot display any relevant data for that order. This typically occurs in the context of capacity planning or production planning when the system is trying to evaluate the requirements for a particular order but finds none.
Cause:
- No Planned Orders or Production Orders: The order in question may not have any associated planned orders or production orders that require capacity.
- Incorrect Evaluation Period: The evaluation period set in the planning or reporting transaction may not cover the time frame in which the order has requirements.
- Order Status: The order may be in a status that does not allow for requirements to be displayed (e.g., completed, closed).
- Missing or Incorrect Data: There may be missing data in the order or related master data (e.g., material master, routing) that prevents the system from identifying any requirements.
- Capacity Planning Settings: The settings for capacity planning may not be configured correctly, leading to no requirements being generated for the order.
Solution:
- Check Order Details: Review the order to ensure that it has planned orders or production orders associated with it. If not, create the necessary orders.
- Adjust Evaluation Period: Ensure that the evaluation period is set correctly in the transaction you are using. Adjust the dates to include the time frame relevant to the order.
- Review Order Status: Check the status of the order. If it is completed or closed, you may need to reopen it or create a new order if further processing is required.
- Verify Master Data: Ensure that all relevant master data (material master, routing, work center) is complete and accurate. Missing or incorrect data can lead to issues in requirement generation.
- Check Capacity Planning Settings: Review the configuration settings for capacity planning in your SAP system to ensure they are set up correctly to generate requirements for orders.
Related Information:
If the issue persists after checking these areas, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and control.
Get instant SAP help. Start your 7-day free trial now.
CY138
In the evaluation period no labor has been assigned to the capacity
What causes this issue? An evaluation period is defined in the time profile. However, no labor assignment is defined for the capacity in this evaluat...
CY137
No objects have been selected. Function not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CY140
No capacity requirements were found in the evaluation period
What causes this issue? No capacity requirements records were found for the selected orders in the evaluation period.How to fix this error? You shou...
CY141
The orders entered do not exist
What causes this issue? The orders entered in the initial screen do not exist. The system issues an error message and will not allow you to continue ...