Message type: E = Error
Message class: CP - Task list messages: Core data
Message number: 208
Message text: Change number & collision with available change number &
During the date shift, the change status, which is shifted with change
number &V1&, collided with an existing change status with the change
number &V2&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
CP208
- Change number & collision with available change number & ?The SAP error message CP208 indicates a collision between change numbers in the context of change management, particularly when working with change numbers in the SAP system. This error typically arises when there is an attempt to assign a change number that conflicts with an existing change number in the system.
Cause: The error CP208 occurs due to one of the following reasons: Change Number Conflict: The change number you are trying to use is already assigned to another object or is in use in a way that conflicts with the current operation. Incorrect Change Number Status: The change number may not be in the correct status for the operation you are trying to perform (e.g., it may be locked or not released). System Configuration: There may be configuration settings in the system that prevent the use of certain change numbers under specific conditions.
Solution: To resolve the CP208 error, you can take the following steps: Check Existing
Get instant SAP help. Sign up for our Free Essentials Plan.
CP207
Change number &1 exceeds the material-routing assignment change status &2
What causes this issue? During the date shift, the change status of the material-routing assignment, shifted with the change number &, exceeds an...
CP206
Change number & collision with Mat.-routing assignment change status &
What causes this issue? During the date shift, the change status of the material routing assignment which is shifted with change number &V1&,...
CP209
Change number & exceeds existing change status (Number&)
What causes this issue? During the date shift, a change status, shifted with the change number &V1&, exceeds an existing change status with t...
CP210
Change number & collsion with PRT to this operation (Change number &)
What causes this issue? During the date shift, a PRT assignment which is shifted with change number &V1&, collided with an existing change st...
Click on this link to search all SAP messages.