Message type: E = Error
Message class: COOS - Order Split
Message number: 018
Message text: Confirmations were created at header level for order &
Order header confirmations have already been created. However, after an
order split only operation confirmations are possible.
A combination of operation confirmations and order header confirmations
within an order is not possible.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
To be able to split the order, proceed as follows:
RESET N1
Cancel the order header confirmations.
Create confirmations for the operations to regain the previous
confirmation status.
Error message extract from SAP system. Copyright SAP SE.
COOS018
- Confirmations were created at header level for order & ?The SAP error message COOS018 indicates that confirmations were created at the header level for a production order, which means that the system is trying to process confirmations for operations that have already been confirmed at the header level. This can occur in various scenarios, such as when trying to confirm operations individually after a header confirmation has already been made.
Cause:
- Header Confirmation: The most common cause of this error is that the production order has already been confirmed at the header level, which means that all operations under that order have been confirmed collectively.
- Incorrect Confirmation Process: Attempting to confirm individual operations after a header confirmation can lead to this error.
- System Configuration: There may be specific settings in the system that enforce header-level confirmations, preventing individual operation confirmations.
Solution:
- Check Confirmations: Verify if the production order has already been confirmed at the header level. You can do this by checking the confirmation history in the production order.
- Avoid Duplicate Confirmations: If the order has been confirmed at the header level, you should not attempt to confirm individual operations. Instead, ensure that all necessary data is included in the header confirmation.
- Use the Correct Confirmation Method: If you need to confirm operations individually, you may need to reverse the header confirmation (if applicable) and then confirm the operations as needed.
- Consult Documentation: Review the SAP documentation or help files related to production order confirmations to understand the correct procedures and implications of header vs. operation confirmations.
- System Configuration Review: If this behavior is not expected, consult with your SAP Basis or configuration team to review the settings related to confirmations in your SAP system.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and control.
Get instant SAP help. Start your 7-day free trial now.
COOS017
Determined quantity of serial numbers to be split off is not a whole no.
What causes this issue? The specified split quantity of &V1& leads to a quantity of &V2& serial numbers that are to be split off. &am...
COOS016
Select &2 serial numbers, not &1
What causes this issue? The number of serial numbers that you have selected to be split off ( &V1&) does not correspond to the number of seri...
COOS019
Operation &1 has already been deleted
What causes this issue? You have selected an operation that has already been deleted as a split operation. However, you are not allowed to do this.Sy...
COOS020
You cannot delete operation &1 because it has already been split
What causes this issue? The operation to be deleted has already been split within an order split. Split operations cannot be deleted.System Response ...
Click on this link to search all SAP messages.