Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 726
Message text: Component & & is already released
You have attempted to change the account assignment of a component.
A purchase requisition or a reservation that is relevant to MRP exists.
In this situation, the system will not let you change the account
assignment.
INCLUDE 'NA_ALLG_NOFUNKTION' OBJECT DOKU ID TX
If you want to change the account assignment of the component, you must
first delete it and then allocate it again.
Error message extract from SAP system. Copyright SAP SE.
CN726
- Component & & is already released ?The SAP error message CN726, which states "Component & & is already released," typically occurs in the context of project management or production planning within SAP. This error indicates that the specified component (material or part) is already in a released status, meaning it cannot be released again or modified in the way you are attempting.
Cause:
- Component Status: The component you are trying to release is already marked as released in the system. This can happen if the release process was completed previously.
- Project Management: In project management scenarios, this error can occur if you are trying to release a component that is part of a project that has already been released.
- Data Entry Error: There may be a mistake in the data entry, such as trying to release the same component multiple times.
Solution:
- Check Component Status: Verify the status of the component in the system. You can do this by navigating to the relevant transaction (e.g., CN22 for project management) and checking the status of the component.
- Avoid Duplicate Releases: Ensure that you are not attempting to release the same component multiple times. If it is already released, you may not need to take any further action.
- Review Project Structure: If the component is part of a project, review the project structure to ensure that you are following the correct release process.
- Consult Documentation: Refer to SAP documentation or help files for specific instructions related to the release process for components in your version of SAP.
- Contact Support: If you are unable to resolve the issue, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.
Related Information:
By following these steps, you should be able to address the CN726 error effectively.
Get instant SAP help. Start your 7-day free trial now.
CN725
Enter account assignment category for purc. req/reservation
What causes this issue? You are attempting to externally obtain or internally reserve a component. In order to select and control the appropriate acc...
CN724
An MRP-relevant reservation exists for & &
What causes this issue? You are attempting to change the allocation of a component to a WBS element.System Response Note that a planned order or pro...
CN727
Material & only for individual requirements (check entry)
What causes this issue? You want to allocate components to the activity. However, you cannot use these components in collective stock: You maintained...
CN728
Enter movement types for project management/networks
What causes this issue? The table <LS>movement types</> has not been maintained for project management in Customizing. The system needs ...
Click on this link to search all SAP messages.