Do you have any question about this error?
Message type: E = Error
Message class: CN - Meldungen für Netzpläne
Message number: 071
Message text: Activity can only differ between internal and external processing
The company code determined by the plant in the activity element does
not agree with the company code of the activity.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Enter a plant for the activity element that has the same company code
as the activity.
Error message extract from SAP system. Copyright SAP SE.
CN071
- Activity can only differ between internal and external processing ?The SAP error message CN071 ("Activity can only differ between internal and external processing") typically occurs in the context of project management and controlling, particularly when dealing with activity types in SAP Project System (PS) or Controlling (CO) modules. This error indicates that there is a mismatch in the configuration of activity types, specifically regarding how they are defined for internal and external processing.
Cause:
The error arises when you attempt to assign an activity type to a cost element or a project that has inconsistent settings for internal and external processing. In SAP, activity types can be configured to have different rates or settings based on whether they are used for internal or external purposes. If the system detects that the settings for an activity type are not aligned, it will trigger this error.
Solution:
To resolve the CN071 error, you can follow these steps:
Check Activity Type Configuration:
- Go to the configuration settings for the activity type in SAP.
- Ensure that the settings for internal and external processing are consistent. This includes checking the cost rates, cost elements, and any other relevant parameters.
Review Project Settings:
- Check the project definition and ensure that the activity types assigned to the project are correctly configured for the intended processing type (internal or external).
- Make sure that the project is set up to use the correct activity types based on the processing type you are trying to execute.
Cost Element Assignment:
- Verify that the cost elements associated with the activity types are correctly assigned and that they match the intended processing type.
Consult Documentation:
- Review SAP documentation or help resources related to activity types and project management to ensure that you are following best practices.
Testing:
- After making the necessary adjustments, test the changes by attempting to execute the transaction that previously resulted in the error.
Consult with SAP Support:
- If the issue persists after checking the configurations, consider reaching out to SAP support or your internal SAP team for further assistance.
Related Information:
KP26
(Change Activity Type Planning) or CJ20N
(Project Builder) to review and modify the relevant settings.By following these steps, you should be able to identify and resolve the cause of the CN071 error in your SAP system.
Get instant SAP help. Start your 7-day free trial now.
CN070
WBS elem. cntrl. area & is not same as act. elem. cntr. area &
What causes this issue? Controlling area of the WBS element (&V1) must agree with the controlling area of the activity element (&V2&). Th...
CN069
WBS elem. cntrl. area & is not same as activity cntrl. area &
What causes this issue? Controlling area of the WBS element (&V1) does not agree with the controlling area of the activity (&V2&). They m...
CN072
Plant & is not assigned to company code & of activity
What causes this issue? The plant to which the material is allocated, is different from the plant in the activity and is not allocated to the company...
CN073
PS text cannot be copied since it does not have SAPScript format
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.