Do you have any question about this error?
Message type: E = Error
Message class: CM - Task list messages: Material component allocations
Message number: 113
Message text: This component is not allocated to an operation.
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
CM113
- This component is not allocated to an operation. ?The SAP error message CM113 ("This component is not allocated to an operation") typically occurs in the context of production planning and control, particularly when working with production orders or process orders. This error indicates that a specific component (material) is not assigned to any operation within the routing or production order.
Causes:
- Missing Allocation: The component has not been allocated to any operation in the routing or production order.
- Incorrect Routing: The routing used for the production order does not include the component in question.
- Changes in Routing: If the routing was changed after the production order was created, the component may not be included in the updated routing.
- Component Not Defined: The component may not be defined in the bill of materials (BOM) for the material being produced.
- Order Type Issues: The order type may not support the allocation of the component.
Solutions:
- Check Routing: Verify that the routing for the production order includes the component. You can do this by navigating to the routing in the SAP system and checking the operations and their assigned components.
- Update Production Order: If the routing has changed, you may need to update the production order to reflect the new routing. This can be done by re-releasing the order or adjusting the components manually.
- Check BOM: Ensure that the component is correctly defined in the BOM for the material. If it is missing, you will need to add it to the BOM.
- Reallocate Components: If the component is not allocated, you can manually allocate it to the appropriate operation in the production order.
- Consult Documentation: Review any relevant documentation or guidelines for the specific production process to ensure compliance with standard practices.
Related Information:
CO02
(Change Production Order) or CS02
(Change BOM) to make necessary adjustments.By following these steps, you should be able to resolve the CM113 error and ensure that your production processes run smoothly.
Get instant SAP help. Start your 7-day free trial now.
CM112
No valid operation found.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CM111
No valid routing found.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CM114
No material components are allocated to operation
What causes this issue? You cannot branch to the overview of material components allocated to the operation because there are no components of the cu...
CM115
Multiple allocations are not allowed in the std. seq. or parallel seq.
What causes this issue? You have carried out one of the following actions: You checked consistency of component allocation in the routing. The BOM it...
Click on this link to search all SAP messages.