Do you have any question about this error?
Message type: E = Error
Message class: CKMLMV - Message class for quantity structure tool
Message number: 024
Message text: Material sucessfully costed with reduced BOM
You have performed multi-level price determination with the indicator
<DS:DE.CKML_CUTBOM>Reduced actual BOM</>.
An error occured in the first step with at least one procurement
alternative when costing the material (negative price or a change that
exceeded the percentage threshold, for example).
The actual BOM was reduced for this procurement alternative so that the
material price can be determined sucessfully with multi-level price
determination.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
CKMLMV024
- Material sucessfully costed with reduced BOM ?The SAP error message CKMLMV024 indicates that a material has been successfully costed, but the system has used a reduced Bill of Materials (BOM) for the costing process. This typically occurs in the context of Material Ledger (ML) and can be related to various factors in the costing process.
Cause:
- BOM Changes: The BOM for the material may have been changed or reduced, leading to a situation where not all components are included in the costing.
- Costing Variant Settings: The settings in the costing variant may allow for the use of a reduced BOM under certain conditions.
- Material Master Data: The material master data may not be correctly set up, leading to discrepancies in the BOM used for costing.
- Version Control: If there are multiple versions of the BOM, the system may have defaulted to a version that is incomplete or reduced.
- Costing Run Parameters: The parameters set during the costing run may have specified the use of a reduced BOM.
Solution:
- Review BOM: Check the BOM for the material in question to ensure that it is complete and accurate. Make sure all necessary components are included.
- Check Costing Variant: Review the settings of the costing variant being used to ensure that it is configured correctly and does not inadvertently allow for reduced BOMs.
- Material Master Review: Verify the material master data to ensure that all relevant information is correctly maintained.
- Costing Run Parameters: Review the parameters used in the costing run to ensure that they align with your business requirements and do not allow for reduced BOMs unless intended.
- Consult Documentation: Refer to SAP documentation or help resources for specific details on the error message and its implications.
- Testing: If changes are made, perform a test costing run to ensure that the issue is resolved and that the correct BOM is being used.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with an SAP expert or your organization's SAP support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
CKMLMV023
Procurement alternative does not need to be corrected
What causes this issue? You have performed multi-level price determination with the indicator <DS:DE.CKML_CUTBOM>Reduced actual BOM</> se...
CKMLMV022
A target BOM was created for the procurement process
What causes this issue? You have performed multi-level material settlement with the indicator <DS:DE.CKML_CUTBOM>Reduced actual BOM</> se...
CKMLMV025
More material prices need to be determined with multi-level determination
What causes this issue? You indicated that all material prices should be determined again upon multi-level material price determination.System Respon...
CKMLMV026
&1 materials were converted for table &2
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.