Do you have any question about this error?
Message type: E = Error
Message class: CKBA - Message Pool for Development Class CKBA
Message number: 052
Message text: BOM & and routing & are not suitable for production version &
The data in the BOM, routing and production version in the procurement
alternative is not compatible.
In joint production, the co-product and process material are checked to
see if they contain different quantity structure data. For example, the
procurement alternative of the co-product can contain a production
version, and the process material can contain a BOM or routing, or vice
versa. The system then checks whether the corresponding data for the
BOM and routing is maintained in the production version belonging to
the process material.
If this is not the case, this message is sent.
Either correct the production version for your process material, or
delete the procurement alternative.
Error message extract from SAP system. Copyright SAP SE.
CKBA052
- BOM & and routing & are not suitable for production version & ?The SAP error message CKBA052 indicates that there is an issue with the Bill of Materials (BOM) and routing not being suitable for the specified production version. This error typically arises in the context of production planning and execution when the system cannot find a valid BOM or routing that corresponds to the production version being used.
Causes of CKBA052 Error
- Missing BOM or Routing: The specified production version does not have an associated BOM or routing defined in the system.
- Inactive BOM or Routing: The BOM or routing may exist but is not active for the specified production version.
- Incorrect Production Version: The production version being referenced may not be correctly set up or may not match the material or plant combination.
- Data Inconsistencies: There may be inconsistencies in the master data, such as incorrect configuration or missing links between the production version, BOM, and routing.
- Plant-Specific Settings: The BOM or routing may be plant-specific, and the production version may not be valid for the plant being used.
Solutions to CKBA052 Error
Check BOM and Routing:
- Go to the BOM (transaction CS03) and routing (transaction CA03) to verify if they exist for the material and plant combination.
- Ensure that the BOM and routing are active and correctly assigned to the production version.
Verify Production Version:
- Check the production version (transaction C223) to ensure it is correctly set up and linked to the appropriate BOM and routing.
- Make sure that the production version is valid for the material and plant in question.
Activate BOM and Routing:
- If the BOM or routing is inactive, activate them using the appropriate transactions (CS02 for BOM and CA02 for routing).
Check Validity Dates:
- Ensure that the validity dates for the BOM, routing, and production version are correct and that they overlap with the current date.
Review Configuration:
- If you have access to configuration settings, review the settings related to production versions, BOMs, and routings to ensure they are correctly configured.
Consult Documentation:
- Refer to SAP documentation or help resources for additional guidance on BOM and routing setup.
Related Information
By following these steps, you should be able to identify the root cause of the CKBA052 error and implement the necessary corrections to resolve it.
Get instant SAP help. Start your 7-day free trial now.
CKBA051
Alternative & cannot be deleted (database problems)
What causes this issue? The procurement alternative could not be deleted.System Response Problems with the database upon trying to delete the procur...
CKBA050
Lot size & is outside lot-size range of routing
What causes this issue? The stated lot size &V1& exceeds the lot size range of &V2& to &V3& in the routing.System Response A...
CKBA055
Material & costed without quantity structure
What causes this issue? You are attempting to create a procurement alternative for a material assigned to a <DS:GLOS.material_type>material typ...
CKBA056
Deletion not possible
What causes this issue? An internal error has occurred.System Response Procurement alternatives cannot be deleted.How to fix this error? Please con...
Click on this link to search all SAP messages.