Message text: No BOM or routing for production version &
There is no BOM or routing for this production version.
The system is attempting to assign a BOM and routing from a production
version of a process material to a procurement alternative of a
co-product. This was unsucessful because a BOM and routing are not
maintained for the production version.
Maintain the appropriate production version.
Error message extract from SAP system. Copyright SAP SE.
CKBA049
- No BOM or routing for production version & ?The SAP error message CKBA049 indicates that there is no Bill of Materials (BOM) or routing available for the specified production version of a material. This error typically occurs during the production planning or costing processes when the system is unable to find the necessary data to proceed with the operation.
Cause:
- Missing BOM: The production version does not have an associated BOM defined in the system.
- Missing Routing: The production version lacks a routing, which is necessary for determining the production process.
- Incorrect Production Version: The production version specified may not be valid or may not exist in the system.
- Data Inconsistency: There may be inconsistencies in the master data, such as the material master or production version settings.
- Plant-Specific Data: The BOM or routing may not be defined for the specific plant where the production is being planned.
Solution:
- Check Production Version: Verify that the production version specified in the transaction is correct and exists in the system.
- Create/Update BOM: If the BOM is missing, create or update the BOM for the material in the relevant plant using transaction code CS01 (Create BOM) or CS02 (Change BOM).
- Create/Update Routing: If the routing is missing, create or update the routing for the material using transaction code CA01 (Create Routing) or CA02 (Change Routing).
- Check Material Master: Ensure that the material master data is complete and correctly configured, especially the production version settings.
- Plant-Specific Configuration: Make sure that the BOM and routing are defined for the specific plant where the production is being executed.
- Use Transaction CK11N: You can use transaction CK11N (Create Cost Estimate with Quantity Structure) to check if the BOM and routing are correctly assigned to the production version.
Related Information:
By following these steps, you should be able to resolve the CKBA049 error and ensure that the necessary BOM and routing are in place for the production version.
Get instant SAP help. Start your 7-day free trial now.
CKBA048
Change not required
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CKBA047
Check reveals no inconsistencies
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CKBA050
Lot size & is outside lot-size range of routing
What causes this issue? The stated lot size &V1& exceeds the lot size range of &V2& to &V3& in the routing.System Response A...
CKBA051
Alternative & cannot be deleted (database problems)
What causes this issue? The procurement alternative could not be deleted.System Response Problems with the database upon trying to delete the procur...