Message text: Material &1 &2 does not contain any segment for in-house production
No segment for in-house production has been created for material &v1&
in plant &v2&
<DS:GLOS.3526B770AFAB52B9E10000009B38F974>Marking</> for this cost
estimate is not carried out.
In transaction <DS:TRAN.MM01>Material master</> create the segment for
in-house production for this material (material for valuation type &v3&
) with costing view and accounting view and allow the cost estimate.
In Customizing <LS>Materials Management</> check under <LS>Valuation
and Account Assignment -> Split Valuation -> Configure Split Valuation
</> the valuation type which was used here. This always requires the
availability of an in-house production segment.
Error message extract from SAP system. Copyright SAP SE.
CK862
- Material &1 &2 does not contain any segment for in-house production ?The SAP error message CK862 indicates that the specified material does not have any segment defined for in-house production in the material master or the relevant configuration. This typically occurs in the context of product costing, where the system expects to find cost information for in-house production but cannot locate it.
Cause:
- Missing Costing Data: The material may not have been set up with the necessary costing data for in-house production.
- Incorrect Material Type: The material type may not be configured to allow for in-house production.
- Costing Variant Issues: The costing variant being used may not be set up correctly to include in-house production.
- Missing Segments: The material master may not have the required segments (like costing view) populated for in-house production.
Solution:
Check Material Master:
- Go to the material master (transaction code
MM03
) and check the costing view. Ensure that the in-house production segment is populated.- If the costing view is missing, you may need to create or update the material master data (transaction code
MM01
orMM02
).Review Costing Variant:
- Check the costing variant settings (transaction code
OKKN
) to ensure that it is configured to include in-house production costs.Check Material Type Configuration:
- Ensure that the material type allows for in-house production. This can be checked in the configuration settings (transaction code
SPRO
).Create Costing for the Material:
- If the material is new or has not been costed yet, you may need to run a costing run (transaction code
CK40N
) to create the necessary costing data.Consult Documentation:
- Review SAP documentation or help resources for additional guidance on setting up materials for in-house production.
Related Information:
MM01
: Create MaterialMM02
: Change MaterialMM03
: Display MaterialCK40N
: Create Cost EstimateOKKN
: Costing VariantsBy following these steps, you should be able to resolve the CK862 error and ensure that the material is properly configured for in-house production.
Get instant SAP help. Start your 7-day free trial now.
CK861
Order BOM costing can only be carried out for valuated stock
What causes this issue? Order BOM costing can only be used in connection with valuated sales order stock. Item &v2& of sales document &v1...
CK860
Production version & is still being used in the cost estimate
What causes this issue? You want to delete <DS:GLOS.3526C38DAFAB52B9E10000009B38F974>production version</> &V1& for material &...
CK863
Production version &1 not valid for quantity structure date &2
What causes this issue? You predefined production version &V1&. However, the system recognized that the period of validity of the production ...
CK864
Production version &1 does not match costing lot size &2 &3
What causes this issue? You predefined the <DS:GLOS.3526C38DAFAB52B9E10000009B38F974>Production version</> &V1&. However,the syst...
Click on this link to search all SAP messages.