How To Fix CJ589 - No dates for WBS or project definition exist


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CJ - Project master data and structure

  • Message number: 589

  • Message text: No dates for WBS or project definition exist

  • Show details Hide details
  • What causes this issue?

    There must be a time frame in order for you to enter activities for a
    WBS element.
    It can come from the:
    WBS element
    superior WBS element in the hierarchy
    project definition

    System Response

    INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX

    How to fix this error?

    Maintain the dates in the WBS element or in the superior WBS element.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CJ589 - No dates for WBS or project definition exist ?

    The SAP error message CJ589 ("No dates for WBS or project definition exist") typically occurs when you are trying to perform an action related to a Work Breakdown Structure (WBS) element or project definition, but the system cannot find any valid dates associated with it. This can happen in various scenarios, such as when you are trying to create or modify a project, or when you are attempting to assign costs or resources.

    Causes:

    1. Missing Dates: The WBS element or project definition does not have any start or finish dates defined.
    2. Incorrect Status: The project or WBS element may be in a status that does not allow for date assignment.
    3. Project Definition Not Created: The project definition may not have been created properly, leading to missing date information.
    4. Data Inconsistency: There may be inconsistencies in the project data that prevent the system from recognizing valid dates.

    Solutions:

    1. Check Project Definition:

      • Navigate to the project definition in the SAP system and ensure that the start and finish dates are correctly defined.
      • You can do this by using transaction code CJ02 (Change Project) or CJ03 (Display Project).
    2. Update Dates:

      • If the dates are missing, you can enter the required start and finish dates in the project definition or WBS element.
      • Ensure that the dates are valid and make sense in the context of the project.
    3. Review Project Status:

      • Check the status of the project or WBS element. If it is in a status that does not allow for changes, you may need to change the status or unlock the project.
    4. Create WBS Element:

      • If the WBS element does not exist, you may need to create it using transaction code CJ01 (Create WBS Element) and ensure that you assign the necessary dates.
    5. Check for Data Consistency:

      • Use transaction code CJEN (Project Management: Check Project) to check for any inconsistencies in the project data.
    6. Consult Documentation:

      • Review any relevant documentation or guidelines for project management in your organization to ensure compliance with required processes.

    Related Information:

    • Transaction Codes:

      • CJ01: Create WBS Element
      • CJ02: Change Project
      • CJ03: Display Project
      • CJEN: Check Project
    • SAP Notes: Check SAP Notes for any known issues or patches related to this error message. You can search for relevant notes in the SAP Support Portal.

    • User Authorization: Ensure that you have the necessary authorizations to make changes to project definitions and WBS elements.

    By following these steps, you should be able to resolve the CJ589 error and ensure that your project or WBS element has the necessary date information.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant