How To Fix CJ588 - WBS elements have later finish date than project definition


SAP Error Message - Details

  • Message type: E = Error

  • Message class: CJ - Project master data and structure

  • Message number: 588

  • Message text: WBS elements have later finish date than project definition

  • Show details Hide details
  • What causes this issue?

    You entered a finish date for the WBS element after the finish date in
    the project definition. Since the start and finish dates in the project
    definition are not binding, processing has not been stopped.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message CJ588 - WBS elements have later finish date than project definition ?

    The SAP error message CJ588 indicates that there are Work Breakdown Structure (WBS) elements within a project that have a later finish date than the project definition itself. This situation can arise due to various reasons, and it can lead to inconsistencies in project planning and reporting.

    Cause:

    1. WBS Element Dates: The finish date of one or more WBS elements is set to a date that is later than the finish date of the overall project definition.
    2. Project Definition Changes: If the project definition's finish date was changed after the WBS elements were created, the WBS elements may not have been updated accordingly.
    3. Incorrect Planning: During the planning phase, WBS elements may have been assigned dates that do not align with the project definition.
    4. Manual Entry Errors: Users may have manually entered incorrect dates for WBS elements.

    Solution:

    To resolve the CJ588 error, you can take the following steps:

    1. Check Project Definition Dates:

      • Go to the project definition in SAP and verify the finish date.
      • Ensure that it is set correctly according to the project timeline.
    2. Review WBS Elements:

      • Navigate to the WBS elements associated with the project.
      • Check the finish dates of each WBS element to identify which ones are causing the issue.
    3. Adjust WBS Element Dates:

      • If you find WBS elements with finish dates later than the project definition, adjust their finish dates to be in line with the project definition.
      • You can do this by editing the WBS element in the project structure.
    4. Recalculate Dates:

      • If you have made changes to the project definition or WBS elements, you may need to recalculate the dates to ensure consistency across the project.
    5. Use Project Planning Tools:

      • Utilize SAP project planning tools to help visualize and manage the project timeline effectively. This can help prevent similar issues in the future.
    6. Consult Documentation:

      • Refer to SAP documentation or help resources for additional guidance on managing project definitions and WBS elements.

    Related Information:

    • Transaction Codes: You can use transaction codes like CJ20N (Project Builder) or CJ02 (Change Project) to access and modify project definitions and WBS elements.
    • Project Management Best Practices: Regularly review project timelines and ensure that all elements are aligned to avoid discrepancies.
    • User Training: Ensure that users involved in project planning are trained on how to properly set and adjust dates in SAP to minimize errors.

    By following these steps, you should be able to resolve the CJ588 error and ensure that your project planning is accurate and consistent.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant