Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 565
Message text: MRP controller &2 does not exist in plant &1
The MRP controller &v2&, who you entered in the newtwork profile, does
not work in plant &v1&. Therefore you cannot create activities for the
WBS element.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
Enter a correct MRP controller in the network profile.
Choose <ls>Settings -> Options</> and change the MRP controller on the
"Control" tab page.
Error message extract from SAP system. Copyright SAP SE.
CJ565
- MRP controller &2 does not exist in plant &1 ?The SAP error message CJ565 indicates that the MRP (Material Requirements Planning) controller specified does not exist in the specified plant. This error typically arises in the context of project management and production planning when trying to assign or reference an MRP controller that has not been defined in the system for the given plant.
Cause: Missing MRP Controller: The MRP controller you are trying to use has not been created or is not assigned to the specified plant. Incorrect Configuration: There may be a configuration issue where the MRP controller is not properly linked to the plant in the system. Data Entry Error: There could be a typographical error in the MRP controller code or plant code being used.
Solution: Check MRP Controller Configuration: Go to the transaction code OMC1 (or SPRO -> Production -> MRP -> MRP Controller -> Define MRP Controllers) to verify if the MRP controller exists. Ensure that the MRP controller is assigned
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ564
Enter start and finish date
What causes this issue? You have only entered one date for the WBS element (either the start or the finish date) however both dates are required for ...
CJ563
Finish date is earlier than start date
What causes this issue? You entered a finish date for the WBS element that is earlier than the start date of the WBS element.System Response INCLUDE...
CJ566
Plant cannot be determined. Please check profile
What causes this issue? You have entered a key for a plant in the project profile which the system does not recognize.System Response INCLUDE '...
CJ567
There are no activities for the selected WBS elements
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...