Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 567
Message text: There are no activities for the selected WBS elements
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
CJ567
- There are no activities for the selected WBS elements ?The SAP error message CJ567 ("There are no activities for the selected WBS elements") typically occurs in the context of project management within SAP, particularly when working with Work Breakdown Structure (WBS) elements in Project System (PS) module. This error indicates that the system cannot find any activities associated with the specified WBS elements.
Causes:
No Activities Created: The most common reason for this error is that no activities have been created for the selected WBS elements. Activities must be defined for each WBS element to perform certain operations.
Incorrect WBS Element: The WBS element you are trying to access may not have any associated activities, or you may have selected the wrong WBS element.
Status of WBS Element: The WBS element may be in a status that does not allow for activities to be displayed or created (e.g., it may be locked or not released).
Authorization Issues: There may be authorization issues preventing you from viewing the activities associated with the WBS element.
Data Consistency Issues: There could be inconsistencies in the data, such as missing links between the WBS element and its activities.
Solutions:
Create Activities: If no activities exist, you need to create them. You can do this by navigating to the project management transaction (e.g., CJ20N) and adding activities to the relevant WBS element.
Check WBS Element: Verify that you have selected the correct WBS element. You can do this by checking the hierarchy or using the project structure.
Review Status: Check the status of the WBS element. Ensure that it is in a status that allows for activities to be created or displayed. You may need to change the status if it is locked.
Authorization Check: Ensure that you have the necessary authorizations to view and manage activities for the WBS element. You may need to contact your SAP security team for assistance.
Data Consistency Check: If you suspect data inconsistencies, you may need to run consistency checks or consult with your SAP Basis or technical team to resolve any underlying issues.
Use Transaction Codes: Use transaction codes like CJ20N (Project Builder) or CJ03 (Display WBS) to navigate and check the details of the WBS elements and their associated activities.
Related Information:
By following these steps, you should be able to identify the cause of the CJ567 error and implement the appropriate solution.
Get instant SAP help. Start your 7-day free trial now.
CJ566
Plant cannot be determined. Please check profile
What causes this issue? You have entered a key for a plant in the project profile which the system does not recognize.System Response INCLUDE '...
CJ565
MRP controller &2 does not exist in plant &1
What causes this issue? The MRP controller &v2&, who you entered in the newtwork profile, does not work in plant &v1&. Therefore you ...
CJ568
WBS element &1: Activity &2 in network &3 is not in time frame
What causes this issue? Activity &V2& in network &V3& no longer lies within the time frame of WBS element &V1&.How to fix thi...
CJ569
Project structure contains several calendars
What causes this issue? You have entered different factory calendars for the dates of the individual WBS elements. You could get dates for the WBS el...