Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 564
Message text: Enter start and finish date
You have only entered one date for the WBS element (either the start or
the finish date) however both dates are required for time scheduling.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Enter the missing start or finish date for the WBS element.
Error message extract from SAP system. Copyright SAP SE.
CJ564
- Enter start and finish date ?The SAP error message CJ564, which states "Enter start and finish date," typically occurs in the context of project management within the SAP system, particularly when dealing with project definitions, work breakdown structures (WBS), or network activities. This error indicates that the system requires both a start date and a finish date to proceed with the operation you are attempting to perform.
Cause: Missing Dates: The most common cause of this error is that the user has not entered the required start and finish dates for a project, WBS element, or network activity. Incorrect Data Entry: Dates may have been entered incorrectly or in an invalid format. System Configuration: There may be configuration settings in the project management module that require dates to be filled in for certain operations.
Solution: Enter Dates: Ensure that you enter both the start date and finish date in the relevant fields. This can usually be done in the project definition
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ563
Finish date is earlier than start date
What causes this issue? You entered a finish date for the WBS element that is earlier than the start date of the WBS element.System Response INCLUDE...
CJ562
Level dates for all activities first
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ565
MRP controller &2 does not exist in plant &1
What causes this issue? The MRP controller &v2&, who you entered in the newtwork profile, does not work in plant &v1&. Therefore you ...
CJ566
Plant cannot be determined. Please check profile
What causes this issue? You have entered a key for a plant in the project profile which the system does not recognize.System Response INCLUDE '...
Click on this link to search all SAP messages.