Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 553
Message text: No basic dates exist. Forecast dates for & not possible
You can maintain forecast dates for the WBS only after you have main-
tained the basic dates.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Enter the basic dates.
Error message extract from SAP system. Copyright SAP SE.
CJ553
- No basic dates exist. Forecast dates for & not possible ?The SAP error message CJ553: No basic dates exist. Forecast dates for & not possible typically occurs in the context of project management within SAP, particularly when dealing with project planning and scheduling. This error indicates that the system cannot find any basic dates for the specified project or WBS (Work Breakdown Structure) element, which are necessary for generating forecasts.
Cause:
- Missing Basic Dates: The most common cause of this error is that the project or WBS element does not have any basic dates defined. Basic dates are essential for scheduling and forecasting activities in SAP.
- Project Status: The project might be in a status that does not allow for date assignment or forecasting.
- Incorrect Configuration: There may be configuration issues in the project management settings that prevent the assignment of basic dates.
- Data Entry Errors: There could be errors in data entry or missing information in the project definition.
Solution:
Check Basic Dates:
- Navigate to the project or WBS element in question and check if basic dates (start date, finish date) are defined.
- If they are missing, you will need to enter the basic dates in the project definition or WBS element.
Update Project Status:
- Ensure that the project is in a status that allows for date assignment. If the project is locked or in a closed status, you may need to change it to an open status.
Review Configuration:
- Check the configuration settings in the project management module to ensure that everything is set up correctly for date assignment and forecasting.
Data Validation:
- Validate all entries related to the project to ensure that there are no missing or incorrect fields that could be causing the issue.
Use Transaction Codes:
- You can use transaction codes like CJ20N (Project Builder) or CJ02 (Change Project) to access and modify project details, including basic dates.
Consult Documentation:
- Refer to SAP documentation or help resources for additional guidance on managing project dates and resolving related errors.
Related Information:
By following these steps, you should be able to resolve the CJ553 error and successfully manage your project dates and forecasts in SAP.
Get instant SAP help. Start your 7-day free trial now.
CJ552
No activities exist for the selected WBS elements
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ551
Enter dates in the project definition first
What causes this issue? You have not entered any start or finish dates in the project definition. Therefore you do not have a time frame to work with...
CJ554
Dates conflict with the dates of the subordinate WBS elements.
What causes this issue? When you use top-down planning, the superior WBS elements determine the time frame for each subordinate WBS element. However,...
CJ555
Dates for activity elements could not be maintained
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...