Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 551
Message text: Enter dates in the project definition first
You have not entered any start or finish dates in the project
definition. Therefore you do not have a time frame to work with for
planning dates of the individual WBS elements.
You can plan at the individual WBS element level without having had
entered start and finish dates in the project definition,
However, you should make sure you are not outside of the time frame
that project management has set.
INCLUDE 'NA_ALLG_VERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
Enter the start and finish dates in the project definition.
<ZH>or</>
Change the start and finish dates from time scheduling. Select the menu
options <LS>Goto -> Master data -> Project definition</> .
Error message extract from SAP system. Copyright SAP SE.
CJ551
- Enter dates in the project definition first ?The SAP error message CJ551 ("Enter dates in the project definition first") typically occurs when you are trying to perform an action related to a project in SAP Project System (PS) without having defined the start and finish dates for the project definition. This is a common issue when working with project management in SAP.
Cause:
The error arises because the system requires that the project definition (which is the overarching structure for a project) has defined start and end dates before you can proceed with further actions, such as creating or modifying project elements (like WBS elements, networks, etc.). If these dates are not set, the system cannot determine the timeline for the project, leading to this error.
Solution:
To resolve the CJ551 error, follow these steps:
Access the Project Definition:
- Go to the transaction code CJ02 (Change Project) or CJ01 (Create Project) in SAP.
Enter the Project Definition:
- Input the project definition number for the project you are working on.
Set the Dates:
- Navigate to the Basic Data tab or the relevant section where you can enter the project dates.
- Enter the Start Date and Finish Date for the project. Ensure that the dates are valid and make sense in the context of your project timeline.
Save Changes:
- After entering the dates, save your changes.
Retry the Action:
- Go back to the action you were trying to perform that resulted in the error and try again.
Related Information:
By following these steps, you should be able to resolve the CJ551 error and continue with your project management tasks in SAP.
Get instant SAP help. Start your 7-day free trial now.
CJ550
Define network profile first
What causes this issue? You have not entered a network profile in the project profile. Therefore, you cannot detail dates.System Response INCLUDE ...
CJ549
Activity dates exist for WBS element &. You cannot delete
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ552
No activities exist for the selected WBS elements
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ553
No basic dates exist. Forecast dates for & not possible
What causes this issue? You can maintain forecast dates for the WBS only after you have main- tained the basic dates.System Response INCLUDE 'N...
Click on this link to search all SAP messages.